• LNCMO 523 SC Delivered Chinadown(-10)  06-12|Tin Conc. Burmese 20%min IW MengAup(11000)  06-12|Tin Conc. Burmese 30%min IW MengAup(11000)  06-12|Tungsten APT 88.5%min FOB Chinaup(50)  06-12|Tungsten Oxide WO3 99.95%min EXW Chinaup(25000)  06-12|Tin Conc. 60%min Delivered Chinaup(11000)  06-12|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinaup(20)  06-12|Tungsten Oxide WO3 99.95%min FOB Chinaup(50)  06-12|Tin Ingot 99.95%min EXW Chinaup(11000)  06-12|Tin Solder Wire 99.3%min EXW Chinaup(11)  06-12|Tin Solder Bar 60%min EXW Chinaup(7)  06-12|Monazite TREO 54%min In port Chinadown(-1500)  06-12|Selenium Dioxide 98%min Delivered Chinadown(-4)  06-12|Vanadium Pentoxide Flake 98%min EXW Chinadown(-2000)  06-12
  • MGL to invest in LFP project to expand cathode portfolio

    2026-04-10 15:43:09   [Print]
    Tianjin Guoan Mengguli New Materials Science & Technology Co.Asian Metal Copyright8 billion USD264 million, with Phase I and Phase II accounting for approximately RMB700 million USD103 million and RMB 1.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright (MGL) plans to sign an investment agreement with the Administrative Committee of Dazhou High-Tech Industrial Park in Sichuan and invest RMB500 million (USD73.Asian Metal Copyright, Ltd.Asian Metal Copyright19 million) to establish a wholly-owned subsidiary, Sichuan Mengguli New Materials Technology Co.Asian Metal Copyright Equipment commissioning for Phase I is expected to be completed by March 31, 2027.Asian Metal Copyright, Ltd.Asian Metal Copyright Total investment is estimated at RMB1.Asian Metal Copyright The new entity will develop an integrated lithium iron phosphate (LFP) project for fourth-generation and higher products, further strengthening the MGL's product portfolio and enabling full coverage of mainstream cathode materials.

    The project comprises two segments, LFP and iron phosphate. The LFP project will be developed in two phases.Asian Metal Copyright Total investment is projected at RMB 1.Asian Metal Copyright Phase I will build a 50,000tpa LFP production line, followed by Phase II with an additional capacity of 100,000tpa.Asian Metal Copyright Equipment commissioning for Phase I is expected to be completed by March 31, 2027.Asian Metal Copyright Total investment is estimated at RMB1.Asian Metal Copyright The supporting iron phosphate project will also be implemented in two phases, each adding 100,000tpa of capacity.Asian Metal Copyright8 billion (USD264 million), with Phase I and Phase II accounting for approximately RMB700 million (USD103 million) and RMB 1.Asian Metal Copyright, Ltd.Asian Metal Copyright1 billion (USD161 million), respectively.Asian Metal Copyright The project comprises two segments, LFP and iron phosphate.Asian Metal Copyright Equipment commissioning for Phase I is expected to be completed by March 31, 2027.

    The supporting iron phosphate project will also be implemented in two phases, each adding 100,000tpa of capacity. Total investment is projected at RMB 1.Asian Metal Copyright, Ltd.Asian Metal Copyright2 billion (USD176 million), with roughly RMB600 million (USD87.Asian Metal Copyright Equipment commissioning for Phase I is expected to be completed by March 31, 2027.Asian Metal Copyright83 million) allocated to each phase.

    .Asian Metal Copyright Equipment commissioning for Phase I is expected to be completed by March 31, 2027Asian Metal Copyright
    Lithium Iron Phosphate Li 3.9%min Delivered China
    Unit:RMB/mt
    Lithium Iron Phosphate Li 3.9%min Delivered China RMB/mt
    China's ithium iron phosphate producers' suspension number statistics by province by month
    Unit: pcs
      Copyright © Asian Metal Ltd All rights reserved.