Bougouni lithium mine meets annual stripping guidance in advance
2024-12-27 14:28:51 [Print]
On December 23, Bougouni lithium mining project, invested by Hainan Mining, completed the annual stripping plan for 2024 ahead of schedule, with more than 1
Bougouni project is expected to achieve a total stripping of 1.55 million cubic metres and produce 230,000 tonnes of ROM ore in 2024, both exceeding annual guidance.
. 475 million cubic metres of overburden stripped in total, producing 215,000 tonnes of run-of-mine (ROM) ore, which exceeded the annual guidance by 43%.Bougouni project is expected to achieve a total stripping of 1.55 million cubic metres and produce 230,000 tonnes of ROM ore in 2024, both exceeding annual guidance.