• Copper Conc. TC 25%min CIF Chinadown(-3)  07-04|Chrome Lump S.A. 38%min CIF Chinadown(-7)  07-04|Zircon Sand S.A. Zr(Hf)O2 66%min CIF Chinadown(-50)  07-04|Zircon Sand Australian Zr(Hf)O2 66%min In port Chinadown(-50)  07-04|Coal Tar Pitch Coking Value 53%min EXW Chinadown(-100)  07-04|Molybdenum Scrap Cutting 99.95%min Ex-VAT EXW Chinaup(8)  07-04|Yttrium Oxide 99.999%min In warehouse Rotterdamup(0.3)  07-04|Selenium Powder 99.9%min Delivered Indiaup(50)  07-04|Chrome Lump S.A. 38%min In port Chinadown(-1)  07-04|Silico-manganese 60/14 EXW Chinaup(100)  07-04|Silico-manganese 65/17 EXW Chinaup(100)  07-04|Rebar HRB400 20mm In warehouse Guangzhouup(50)  07-04|Flake Graphite +195 EXW Chinadown(-100)  07-04|Ferro-silicon 75%min In warehouse Rotterdamdown(-20)  07-04
  • Tangshan issues production curb and suspension measures

    2019-09-24 17:29:02   [Print]
    It is said that Emergency Management Office of Tangshan reissued measures for production curb and suspension in the National Day holiday and autumn and winter. The outline is as follows:

    Special period: from September 24 to September 30, enterprises should suspend more than 50% of blast furnaces and suspend all sintering machines, shaft furnaces and lime kilns and no resumption is allowed.

    Stage I: from October 1 to November 14, enterprises should suspend 50% of blast furnaces, sintering machines, shaft furnaces and lime klins; if there is alert for heavy pollution weather, 50% of blast furnaces should suspend production and all sintering machines and shaft furnaces should suspend production and 50% of blast furnaces should suspend production five days later and all lime kilns should suspend production.

    Stage II: from November 15 to March 15 of next year, blast furnaces, sintering machines, shaft furnaces and lime kilns enterprises should suspend production in accordance with documents for enterprises in C-level (Xinda suspends 50%); if there is alert for heavy pollution weather, 50% of blast furnaces should suspend production and all sintering machines and shaft furnaces should suspend production and 50% of blast furnaces should suspend production five days later and all lime kilns should suspend production.

    Other period: after March 15, according to technological guide, if there is alert for heavy pollution weather, sintering machines and shaft furnaces in C-level enterprises should suspend production; five days later, the enterprises should suspend 50% of shaft furnaces, 50% of blast furnaces and all lime kilns.
    .Asian Metal Copyright The outline is as follows: Special period: from September 24 to September 30, enterprises should suspend more than 50% of blast furnaces and suspend all sintering machines, shaft furnaces and lime kilns and no resumption is allowedAsian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.