Progress of key rare earth projects under construction in Ganzhou in February
2017-03-28 16:52:34 [Print]
1. National Engineering Research Center of Efficient Utilization of Iron Rare Earth Resources
Project I: R&D building, personnel dormitory and supporting projects, with a total investment of RMB85 million. Up to this month, the progress of the project is as follows: ① Lab construction completed; some equipment of pilot production line installed and debugged; ② Round-off work on the infrastructure project at this stage; hardening ground surface of R&D building; ③ Waiting for acceptance check notice from the Ministry of Science and Technology; preparing related documents for the check.
Project II: Pilot production line construction project with a total investment of RMB60 million. Progress is as follows: ① Youli Science and Technology’s pre-treatment workshop and precipitation workshop in production; ② G, H, I production lines in the extraction workshop being debugged with other extraction lines in production.
2. Jiangxi Quantong Rare Earth New Science & Technology Co . , Ltd.
Ceramic metal halide (CMH) lamp project with an annual capacity of 10 million and a total investment of RMB233.7 million . Progress is as follows: ① Lamps along two roads in the industrial park have been powered and passed acceptance check; ② Installation of street lamps in the National Engineering Research Center of Efficient Utilization of Iron Rare Earth Resources has passed the acceptance check; ③ The English name of the CMH lamp was rejected because of similar design, and thus its English name has to be redesigned; ④ The company is preparing for the CQC certification.
3. Longnan Yuran Science & Technology Co . , Ltd.
20,000tpy iron oxide red project with a total investment of RMB150 million. Progress is as follows: ① Round-off work on the construction; completing construction of outer wall; preparing for fixing ceramic tiles; around 1/4 of workshop’s roof capped; ② 1/3 of low voltage power distribution system of the plant completed with entire system expected to be installed in mid-March; Contract for high voltage power distribution system signed with the construction to commence; ③ Design of ammonia recovery system and automatic control system completed with contract expected to be signed in mid-March.
4. Ganzhou Qifei New Material Co . , Ltd.
Acid soluble workshop technical transformation project with a total investment of around RMB2.18 million . Progress is as follows: ① Acid soluble workshop already put into use and expected to pass acceptance check in March.
5. Longnan Longyi Heavy Rare-Earth Technology Co . , Ltd.
Technical transformation project of multiple heat-resistance, corrosion-resistance, wear-resistance high performance material production line with an annual capacity of 40,000t of yttrium; total planned investment of RMB200 million, including RMB150 million of fixed assets investment and RMN50 million of circulating fund. Progress is as follows: Hardening workshop’s floor; connecting power and water; infrastructure projects carried out simultaneously; ② large equipment investment with most equipment to be imported; further financing needed for lack of cash.
6. Ganzhou Motaike Tool and Mould Co . , Ltd.
New material tool and mould production line with an annual capacity of 60,000 sets and total planned investment of RMB29.5 million . Progress is as follows: ① Receiving feedback on finished mould, optimizing products; ② Completing initial mold production performance optimization scheme, realizing small-scale production; ③ A batch of finished mould to be produced.
7. Ganzhou Zhonglan Rare Earth New Material Science and Technology Co . , Ltd.
Production line with estimated capacity of 20tpy of new nitride red fluorescent powder and 100tpy of YAG yellow fluorescent powder under construction. Progress is as follows: ① Workshop interlayer almost completed; ② Drawings regarding to positioning of high temperature and high pressure furnace from Shenyang Weitai as well as workshop reformation already delivered to infrastructure department; positioning and debugging to be conducted following the completion of the transformation; ③ Equipment from Shanghai Chenhua and Jiangsu Qianjin in production and to be transported to the workshop within one or two months; ④ Contacting producers for quotations for fluorescence spectroscopy, LED powder detection equipment, vacuum glove boxes and other equipment; procurement expected to be completed in mid-to-late March.
Project I: R&D building, personnel dormitory and supporting projects, with a total investment of RMB85 million. Up to this month, the progress of the project is as follows: ① Lab construction completed; some equipment of pilot production line installed and debugged; ② Round-off work on the infrastructure project at this stage; hardening ground surface of R&D building; ③ Waiting for acceptance check notice from the Ministry of Science and Technology; preparing related documents for the check.
Project II: Pilot production line construction project with a total investment of RMB60 million. Progress is as follows: ① Youli Science and Technology’s pre-treatment workshop and precipitation workshop in production; ② G, H, I production lines in the extraction workshop being debugged with other extraction lines in production.
2. Jiangxi Quantong Rare Earth New Science & Technology Co . , Ltd.
Ceramic metal halide (CMH) lamp project with an annual capacity of 10 million and a total investment of RMB233.7 million . Progress is as follows: ① Lamps along two roads in the industrial park have been powered and passed acceptance check; ② Installation of street lamps in the National Engineering Research Center of Efficient Utilization of Iron Rare Earth Resources has passed the acceptance check; ③ The English name of the CMH lamp was rejected because of similar design, and thus its English name has to be redesigned; ④ The company is preparing for the CQC certification.
3. Longnan Yuran Science & Technology Co . , Ltd.
20,000tpy iron oxide red project with a total investment of RMB150 million. Progress is as follows: ① Round-off work on the construction; completing construction of outer wall; preparing for fixing ceramic tiles; around 1/4 of workshop’s roof capped; ② 1/3 of low voltage power distribution system of the plant completed with entire system expected to be installed in mid-March; Contract for high voltage power distribution system signed with the construction to commence; ③ Design of ammonia recovery system and automatic control system completed with contract expected to be signed in mid-March.
4. Ganzhou Qifei New Material Co . , Ltd.
Acid soluble workshop technical transformation project with a total investment of around RMB2.18 million . Progress is as follows: ① Acid soluble workshop already put into use and expected to pass acceptance check in March.
5. Longnan Longyi Heavy Rare-Earth Technology Co . , Ltd.
Technical transformation project of multiple heat-resistance, corrosion-resistance, wear-resistance high performance material production line with an annual capacity of 40,000t of yttrium; total planned investment of RMB200 million, including RMB150 million of fixed assets investment and RMN50 million of circulating fund. Progress is as follows: Hardening workshop’s floor; connecting power and water; infrastructure projects carried out simultaneously; ② large equipment investment with most equipment to be imported; further financing needed for lack of cash.
6. Ganzhou Motaike Tool and Mould Co . , Ltd.
New material tool and mould production line with an annual capacity of 60,000 sets and total planned investment of RMB29.5 million . Progress is as follows: ① Receiving feedback on finished mould, optimizing products; ② Completing initial mold production performance optimization scheme, realizing small-scale production; ③ A batch of finished mould to be produced.
7. Ganzhou Zhonglan Rare Earth New Material Science and Technology Co . , Ltd.
Production line with estimated capacity of 20tpy of new nitride red fluorescent powder and 100tpy of YAG yellow fluorescent powder under construction. Progress is as follows: ① Workshop interlayer almost completed; ② Drawings regarding to positioning of high temperature and high pressure furnace from Shenyang Weitai as well as workshop reformation already delivered to infrastructure department; positioning and debugging to be conducted following the completion of the transformation; ③ Equipment from Shanghai Chenhua and Jiangsu Qianjin in production and to be transported to the workshop within one or two months; ④ Contacting producers for quotations for fluorescence spectroscopy, LED powder detection equipment, vacuum glove boxes and other equipment; procurement expected to be completed in mid-to-late March.