Capstone cuts copper outlook as Pinto Valley restart slips
2026-11-16 11:07:04 [Print]
Capstone Copper has lowered the bottom of its annual copper production forecast by 5,000 tonnes after delaying the full restart of its Pinto Valley operation in Arizona until mid-December.
The primary crusher needs additional repairs to major mechanical components being manufactured off-site by the original equipment maker, the company said Thursday in an update. Mobile crushers should allow partial processing to resume in mid-November.
The setback puts more pressure on a year-end recovery that Capstone was already counting on. In its Oct. 29 results, the company forecast annual production at the bottom of its 200,000-to-230,000-tonne range, with cash costs at the upper end of guidance.
The revised production floor is 195,000 tonnes. Capstone estimated the additional downtime would reduce this year's copper output by about 5,000 tonnes, depending on restart timing. Temporary mobile crushers could support throughput of up to 40,000 tonnes daily during the interim restart.
That would be about two-thirds of Pinto Valley's nominal milling capacity. The open-pit operation, about 130 km east of Phoenix, has a 60,000-tonne-per-day concentrator and produces copper and molybdenum concentrates as well as copper cathode.
Pinto Valley produced 6,358 tonnes of copper in the third quarter, compared with 9,949 tonnes a year earlier. Its nine-month output was 27,115 tonnes, down from 30,960 tonnes, Capstone reported in October.
The plant had restarted with mobile crushers on Oct. 1 before primary crusher commissioning began Oct. 21. Additional repairs were then identified.
Capstone was looking to higher grades at Mantoverde and Mantos Blancos, alongside completion of the Mantoverde concentrator expansion tie-in, to lift fourth-quarter production. Group output totalled 45,218 tonnes in the third quarter, down 18% from a year earlier.
The primary crusher needs additional repairs to major mechanical components being manufactured off-site by the original equipment maker, the company said Thursday in an update. Mobile crushers should allow partial processing to resume in mid-November.
The setback puts more pressure on a year-end recovery that Capstone was already counting on. In its Oct. 29 results, the company forecast annual production at the bottom of its 200,000-to-230,000-tonne range, with cash costs at the upper end of guidance.
The revised production floor is 195,000 tonnes. Capstone estimated the additional downtime would reduce this year's copper output by about 5,000 tonnes, depending on restart timing. Temporary mobile crushers could support throughput of up to 40,000 tonnes daily during the interim restart.
That would be about two-thirds of Pinto Valley's nominal milling capacity. The open-pit operation, about 130 km east of Phoenix, has a 60,000-tonne-per-day concentrator and produces copper and molybdenum concentrates as well as copper cathode.
Pinto Valley produced 6,358 tonnes of copper in the third quarter, compared with 9,949 tonnes a year earlier. Its nine-month output was 27,115 tonnes, down from 30,960 tonnes, Capstone reported in October.
The plant had restarted with mobile crushers on Oct. 1 before primary crusher commissioning began Oct. 21. Additional repairs were then identified.
Capstone was looking to higher grades at Mantoverde and Mantos Blancos, alongside completion of the Mantoverde concentrator expansion tie-in, to lift fourth-quarter production. Group output totalled 45,218 tonnes in the third quarter, down 18% from a year earlier.