• Zinc Ingot 99.99%min EXW China down(-820)  09-14|Coal Tar Pitch Coking Value 56%min EXW Chinaup(180)  09-14|Tin Conc. Burmese 20%min IW MengAdown(-10000)  09-14|Tin Conc. Burmese 30%min IW MengAdown(-10000)  09-14|Magnesia D.B. 90%min 3-15mm FOB Chinaup(5)  09-14|Tin Conc. 60%min Delivered Chinadown(-10000)  09-14|Tin Ingot 99.95%min EXW Chinadown(-10000)  09-14|Tin Solder Wire 99.3%min EXW Chinadown(-10)  09-14|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max Delivered Chinadown(-3000)  09-14|Tin Solder Bar 60%min EXW Chinadown(-6)  09-14|Lithium Carbonate 99.2%min Delivered Chinadown(-3000)  09-14|Tin Solder Bar 40%min EXW Chinadown(-4)  09-14|Lithium Carbonate 99.5%min Delivered Chinadown(-3000)  09-14|Tin Solder Wire 99%min EXW Chinadown(-10)  09-14
  • Capacity replacement plan issued for No.4 blast furnace overhaul of Ansteel

    2026-09-01 11:31:01   [Print]
    On August 31, the Department of Industry and Information Technology of Liaoning Province publicly released the capacity replacement plan for the green and low-carbon major overhaul project of No.Asian Metal CopyrightOn August 31, the Department of Industry and Information Technology of Liaoning Province publicly released the capacity replacement plan for the green and low-carbon major overhaul project of No.Asian Metal Copyright4 blast furnace at Anshan Iron and Steel Group Co.Asian Metal Copyright Ansteel.Asian Metal Copyright, Ltd.Asian Metal Copyright The project will install one blast furnace of 2580 cubic meters, equivalent to 2,143,000tpa capacity, with construction scheduled to begin in August 2026 and commissioning planned for February 2027.Asian Metal Copyright (Ansteel).Asian Metal CopyrightOn August 31, the Department of Industry and Information Technology of Liaoning Province publicly released the capacity replacement plan for the green and low-carbon major overhaul project of No.Asian Metal Copyright The plan will remain in effect from August 31, 2026, to August 31, 2028.

    The project will install one blast furnace of 2580 cubic meters, equivalent to 2,143,000tpa capacity, with construction scheduled to begin in August 2026 and commissioning planned for February 2027. As part of the capacity replacement, the other one blast furnace of 2580 cubic meters was dismantled in July 2026.

    .Asian Metal Copyright The project will install one blast furnace of 2580 cubic meters, equivalent to 2,143,000tpa capacity, with construction scheduled to begin in August 2026 and commissioning planned for February 2027Asian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.