• Lead Conc. Pb 50%min, Ag 500g/dt max EXW China TCdown(-100)  08-26|Lead Conc. Pb 50%min, Ag 1,000g/dt max EXW China TCdown(-100)  08-26|Lead Conc. Pb 50%min, Ag 200g/dt max EXW China TCdown(-100)  08-26|Germanium Dioxide 99.99%min EXW Chinaup(500)  08-26|Yttrium Oxide 99.999%min IW Rotterdamup(20)  08-26|Coal Tar Pitch Coking Value 56%min EXW Chinaup(150)  08-26|Gadolinium Oxide 99.99%min IW Baltimoreup(8)  08-26|Ferro-tungsten 75%min FOB Chinadown(-5)  08-26|Erbium Oxide 99.5%min IW Rotterdamup(3)  08-26|Silicon Metal 5-5-3 In port Indiaup(3)  08-26|Silicon Metal 4-4-1 In port Indiaup(3)  08-26|Germanium Metal 99.99%min EXW Chinaup(550)  08-26|Cobalt Intermediate 30-40% CIF Chinadown(-0.5)  08-26|Magnesia D.B. 90%min 0-3mm EXW Chinaup(20)  08-26
  • First Tin expands Taronga reserves and eyes longer mine life

    2026-08-17 11:19:14   [Print]
    First Tin has reported a 13% increase in the mineral reserve estimate for its wholly owned Taronga Tin Project in New South Wales, a development that bolsters the project's economics and extends its currently defined operating horizon by approximately one year.

    The updated Proved and Probable Ore Reserves now stand at 45 million tonnes grading 0.12% tin, representing an additional five million tonnes and containing roughly 55,000 tonnes of tin.Asian Metal Copyright The reserve upgrade adds about one year to the mine life as currently defined, strengthening the project's long-term profile.Asian Metal Copyright Within this total, Proven Ore Reserves rose by 19% to 31 million tonnes at 0.Asian Metal Copyright The updated Proved and Probable Ore Reserves now stand at 45 million tonnes grading 0.Asian Metal Copyright13% tin, up from 26 million tonnes at 0.Asian Metal Copyright .Asian Metal Copyright14% tin, for 41,000 tonnes of contained tin.

    A key takeaway from the update is that the additional tonnage falls entirely within the project's already permitted pit boundaries. This means First Tin has effectively expanded its resource base without the need to alter the current pit envelope, a factor that could streamline future development and reduce permitting risks.

    The reserve upgrade adds about one year to the mine life as currently defined, strengthening the project's long-term profile. The Taronga project remains a cornerstone asset for First Tin as it advances toward development, with the latest figures reinforcing its potential as a significant tin producer in Australia.

    .Asian Metal Copyright The reserve upgrade adds about one year to the mine life as currently defined, strengthening the project's long-term profileAsian Metal Copyright
    Tin Solder Bar 60%min EXW China
    Unit:RMB/kg
    Tin Solder Bar 60%min EXW China RMB/kg
    China tin concentrate producers' inventory statistics by province by month
    Unit: mt
      Copyright © Asian Metal Ltd All rights reserved.