• Copper Conc. 25%min CIF China TCdown(-10)  08-14|Tungsten APT 88.5%min FOB Chinaup(50)  08-14|Tungsten Oxide WO3 99.95%min FOB Chinaup(50)  08-14|Ferro-molybdenum 60%min IW Russiaup(90)  08-14|Erbium Oxide 99.5%min FOB Chinaup(2.5)  08-14|Erbium Oxide 99.5%min IW Rotterdamup(2.5)  08-14|Tungsten Bar W-4 99.9%min FOB Chinadown(-5)  08-14|Tungsten Ore WO3 55%min EXW Chinaup(10000)  08-14|Tungsten Ore WO3 50%min FOB Africaup(50)  08-14|Titanium Dioxide Rutile, 93%min FOB Chinadown(-50)  08-14|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinadown(-30)  08-14|Strontium Metal 99%min FOB Chinaup(250)  08-14|Arsenic Trioxide 99%min EXW China down(-30)  08-14|Arsenic Trioxide 99%min FOB China down(-5)  08-14
  • Nantong branch of Zhongtian Steel completes capacity replacement for premium green steel project

    2026-07-14 14:27:44   [Print]
    On July 13, the Department of Industry and Information Technology of Jiangsu Province publicly announced the execution status of the capacity replacement plan for the electric-arc furnace (EAF) short-process premium green steel project of Zhongtian Steel Group (Nantong) Co.Asian Metal Copyright, along with the remaining 42,500tpy of steelmaking capacity from Zhongtian Steel Group Co.Asian Metal Copyright, Ltd.

    The project entails the retirement of two 50-tonne steelmaking converters (with a combined capacity of 1,100,000tpy) from Wuxi Xinsanzhou Special Steel Co., Ltd.Asian Metal Copyright Following on-site verification conducted by the Jiangsu Provincial Department of Industry and Information Technology, in coordination with Nantong municipal authorities, a third-party evaluation team, and industry experts, the newly constructed 100-tonne EAF was confirmed to meet all regulatory requirements.Asian Metal Copyright, along with the remaining 42,500tpy of steelmaking capacity from Zhongtian Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright .Asian Metal Copyright These retired capacities are replaced--on a 1.Asian Metal Copyright The facility's location, company name, equipment model, quantity, and capacity are all fully consistent with the approved replacement plan.Asian Metal Copyright5:1 reduction basis--by one 100-tonne EAF with a capacity of 750,000tpy.Asian Metal Copyright The retired equipment has been dismantled and is no longer capable of resuming production.Asian Metal Copyright The remaining 17,500tpy of steelmaking capacity are retained by the company as a reserve.

    Following on-site verification conducted by the Jiangsu Provincial Department of Industry and Information Technology, in coordination with Nantong municipal authorities, a third-party evaluation team, and industry experts, the newly constructed 100-tonne EAF was confirmed to meet all regulatory requirements. The facility's location, company name, equipment model, quantity, and capacity are all fully consistent with the approved replacement plan.Asian Metal CopyrightOn July 13, the Department of Industry and Information Technology of Jiangsu Province publicly announced the execution status of the capacity replacement plan for the electric-arc furnace EAF short-process premium green steel project of Zhongtian Steel Group Nantong Co.Asian Metal Copyright The retired equipment has been dismantled and is no longer capable of resuming production.