• Zinc Conc. 50%min EXW North China TCdown(-500)  08-28|Zinc Conc. 50%min EXW South China TCdown(-500)  08-28|Lead Conc. Pb 50%min, Ag 3,000g/dt max EXW China TCdown(-300)  08-28|Manganese Ore 38%min FOB S.A. up(0.3)  08-28|Manganese Ore S.A. 37%min In Qinzhou Portup(1)  08-28|Strontium Metal 99%min EXW Chinaup(2500)  08-28|Manganese Ore S.A. 37%min In Tianjin Portup(1)  08-28|Manganese Ore Gabonese 44%min In Qinzhou Portup(1)  08-28|Germanium Dioxide 99.99%min EXW Chinaup(500)  08-28|Strontium Metal 99%min FOB Chinaup(350)  08-28|Manganese Ore S.A. 36%min In Qinzhou Portup(0.9)  08-28|Manganese Ore S.A. 36%min In Tianjin Portup(0.9)  08-28|Manganese Ore Australian 45%min In Qinzhou Portup(1)  08-28|Manganese Ore Brazilian 44%min In Qinzhou Portup(1)  08-28
  • Capacity replacement plan issued for Jiujiang Pinggang's integrated upgrade project

    2026-07-13 15:30:15   [Print]
    Jiangxi Provincial Department of Industry and Information Technology published a public notice on July 10 regarding the capacity replacement plan for the integrated upgrade and revamp project of Jiujiang Pinggang Iron and Steel Co.Asian Metal Copyright The company plans to construct two 2,340-cubic-meter blast furnaces equivalent to a total iron smelting capacity of 3,982,600tpa, as well as one 140-tonne converter, and two 150-tonne converters, representing a total steel smelting capacity of 4,716,700tpa.Asian Metal Copyright, Ltd.Asian Metal Copyright .Asian Metal Copyright The public comment period runs from July 10 to July 31, 2026.

    The company plans to construct two 2,340-cubic-meter blast furnaces equivalent to a total iron smelting capacity of 3,982,600tpa, as well as one 140-tonne converter, and two 150-tonne converters, representing a total steel smelting capacity of 4,716,700tpa. Construction is scheduled to begin in December 2026, with commissioning targeted for December 2028.

    .Asian Metal Copyright, LtdAsian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.