• Copper Conc. 25%min CIF China TCdown(-5)  06-15|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinaup(50)  06-15|Met. Coke A 13%max, S 0.7%max EXW Shanxiup(55)  06-15|Dysprosium Metal 99.5%min EXW Chinaup(50)  06-15|Met. Coke A 13%max, S 0.7%max EXW Hebeiup(55)  06-15|Ferro-dysprosium 80% EXW Chinaup(35)  06-15|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinaup(20)  06-15|Dysprosium Oxide 99.5%min EXW Chinaup(35)  06-15|Met. Coke A 13%max, S 0.7%max EXW Shandongup(55)  06-15|Tungsten Oxide WO3 99.95%min FOB Chinaup(50)  06-15|Tin Conc. Burmese 20%min IW MengAup(10000)  06-15|Tin Conc. Burmese 30%min IW MengAup(10000)  06-15|Graphitized Pet Coke C 98.5%min, S 0.05%max, 1-5mm FOB Chinaup(15)  06-15|Tin Conc. 60%min Delivered Chinaup(10000)  06-15
  • Eldorado Gold achieves first concentrate milestone at McIlvenna Bay

    2026-06-09 11:08:32   [Print]
    Eldorado Gold Corporation announced on June 8 that it has produced first copper concentrate at its wholly owned McIlvenna Bay Project in east-central Saskatchewan, Canada.Asian Metal Copyright The operations team is now focused on ramping up toward the plant's nameplate capacity of 4,900 tonnes per day.Asian Metal Copyright The milestone marks a significant addition to Eldorado's already diversified asset portfolio and further strengthens the company's operating platform in Canada.

    Wet commissioning of the McIlvenna Bay processing plant was completed recently. Following the start of hot commissioning, the first batch of copper concentrate was produced on June 7, 2026.Asian Metal Copyright Following the start of hot commissioning, the first batch of copper concentrate was produced on June 7, 2026.Asian Metal Copyright The operations team is now focused on ramping up toward the plant's nameplate capacity of 4,900 tonnes per day.

    Key activities during the ramp-up phase include optimizing the flotation circuit and reagent addition performance, as well as completing the paste plant and related underground infrastructure-including the paste plant reticulation system-to support ongoing mine and plant production increases. The company expects to achieve commercial production at McIlvenna Bay in the third quarter of 2026.

    .Asian Metal Copyright The operations team is now focused on ramping up toward the plant's nameplate capacity of 4,900 tonnes per dayAsian Metal Copyright
    Copper Rod Ф8mm EXW China PC
    Unit:RMB/mt
    Copper Rod Ф8mm EXW China PC RMB/mt
    China's copper rod producers' inventory statistics by province by month
    Unit: mt
      Copyright © Asian Metal Ltd All rights reserved.