• LNCMO 523 SC Delivered Chinadown(-10)  06-12|Tin Conc. Burmese 20%min IW MengAup(11000)  06-12|Tin Conc. Burmese 30%min IW MengAup(11000)  06-12|Tungsten APT 88.5%min FOB Chinaup(50)  06-12|Tungsten Oxide WO3 99.95%min EXW Chinaup(25000)  06-12|Tin Conc. 60%min Delivered Chinaup(11000)  06-12|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinaup(20)  06-12|Tungsten Oxide WO3 99.95%min FOB Chinaup(50)  06-12|Tin Ingot 99.95%min EXW Chinaup(11000)  06-12|Tin Solder Wire 99.3%min EXW Chinaup(11)  06-12|Tin Solder Bar 60%min EXW Chinaup(7)  06-12|Monazite TREO 54%min In port Chinadown(-1500)  06-12|Selenium Dioxide 98%min Delivered Chinadown(-4)  06-12|Vanadium Pentoxide Flake 98%min EXW Chinadown(-2000)  06-12
  • Dali Dicastal's aluminum alloy wheel hub phase II project in official operation

    2026-06-08 16:09:50   [Print]
    On June 5, with the commissioning of an annual production line capable of producing 5 million aluminum alloy wheel hubs, Dali Dicastal Automotive Parts Co.Asian Metal Copyright The first stage of the phase II project has completed core processes such as melting, casting, and heat treatment.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright (Dali Dicastal) officially launched its phase II project at the Xipi area of the Yunnan Heqing Industrial Park.

    Dali Dicastal is a key production base strategically positioned by CITIC Dicastal in Southwest China. The project first broke ground in Heqing in September 2023.Asian Metal CopyrightOn June 5, with the commissioning of an annual production line capable of producing 5 million aluminum alloy wheel hubs, Dali Dicastal Automotive Parts Co.Asian Metal Copyright The phase I project, with an annual capacity of 3 million aluminum alloy wheel hubs, began construction in October 2023 and was put into operation in January 2024--just 92 days later.

    The newly launched phase II project represents a total planned investment of RMB240 million (USD35.38 million).Asian Metal Copyright, Ltd.Asian Metal Copyright Utilizing existing plant facilities within the industrial park, the project has built an intelligent production line.Asian Metal Copyright The first stage of the phase II project has completed core processes such as melting, casting, and heat treatment.Asian Metal Copyright The first stage of the phase II project has completed core processes such as melting, casting, and heat treatment.Asian Metal Copyright Dali Dicastal officially launched its phase II project at the Xipi area of the Yunnan Heqing Industrial Park.Asian Metal Copyright Subsequent stages will add high-value-added operations including machining and painting, leading to the full setup of a finished wheel hub production line.

    .Asian Metal Copyright38 millionAsian Metal Copyright
    Aluminum Alloy Ingot ADC12 FOB China
    Unit:USD/mt
    Aluminum Alloy Ingot ADC12 FOB China USD/mt
    China secondary aluminum alloy producers' number MoM output increase statistics by province by month
    Unit: pcs
      Copyright © Asian Metal Ltd All rights reserved.