Inner Mongolia Jinebo Fluorine Chemical project begins phase one commissioning
2023-07-31 11:26:03 [Print]
On July 27, Inner Mongolia Jinebo Fluorine Chemical Co
The project will recycle tailings from Baiyun Ebo Iron Mine to produce fluorspar concentrate. The project took 14 months to begin commissioning since the signing of contract, and it filled the blank of fluorine chemical industry in Baotou.
The project has a total production capacity of 300,000tpa, including 120,000tpa for the first phase.
. , Ltd . held the commissioning ceremony for its phase one project at Damao Banner Barun Industrial Park in Baotou, which marked the start of production at the world's largest and state-of-the-art inorganic fluorine chemical project.The project will recycle tailings from Baiyun Ebo Iron Mine to produce fluorspar concentrate. The project took 14 months to begin commissioning since the signing of contract, and it filled the blank of fluorine chemical industry in Baotou.
The project has a total production capacity of 300,000tpa, including 120,000tpa for the first phase.