Taigang Stainless Steel Strip to put into operation first home-made production line soon
2023-03-21 16:36:41 [Print]
Shanxi Taigang Stainless Steel Strip Co
The No. 3 rolling mill project commenced construction on June 15, 2022 with a planned investment of RMB74 . 99 million (USD10 . 90 million) . When it goes into formal production, the company's annul stainless steel production capacity is expected to grow by 9,000t to 33,000t.
. , Ltd . recently put its first home-made production line, No . 3 rolling mill, into commissioning and expects it to be operational at the end of this month.
The No. 3 rolling mill project commenced construction on June 15, 2022 with a planned investment of RMB74 . 99 million (USD10 . 90 million) . When it goes into formal production, the company's annul stainless steel production capacity is expected to grow by 9,000t to 33,000t.