• Copper Cathode 99.99%min Delivered China(4300)  05-20|Copper Conc. 20%min Delivered China(4000)  05-20|Copper Scrap Wire 99%min Delivered China(4000)  05-20|Copper Conc. TC 25%min CIF China(-1)  05-20|Antimony Ingot 99.65%min EXW China(4500)  05-20|Antimony Ingot 99.85%min EXW China(4500)  05-20|Antimony Conc. 50%min Delivered China(3500)  05-20|Antimony Trioxide 99.5%min Delivered China(3500)  05-20|Antimony Trioxide 99.8%min Delivered China(3500)  05-20|Tin Conc. Burmese 20%min In warehouse MengA(7000)  05-20|Indium Ingot 99.995%min Delivered US(8)  05-20|Nickel Cathode 99.96%min EXW China(4500)  05-20|Nickel Cathode Norilsk 99.96%min In port China(4400)  05-20|Tin Conc. Burmese 30%min In warehouse MengA(7000)  05-20
  • AM Statistics: Xinjiang will see 2 million tonnes of aluminum ingot capacity coming on stream in 2015

    2015-01-13 09:13:14   [Print]
    BEIJING (Asian Metal) 13 Jan 15 - According to latest data, there will be more than 2,000,000t of aluminum smelting capacity into operation in Xinjiang in 2015. The outputs of smelting aluminum in Xinjiang are still large, which will have significant impacts on the aluminum ingot prices. The details as the following:

    Company

    Aluminum smelting capacities production in China in 2015 10,000t

    Xinjiang Tianlong Mining Co., Ltd

    10

    Xinjiang Xinfa Group

    55

    Xinjiang Tianshan Aluminum Co., Ltd 

    30-40

    Xinjiang East Hope Nonferrous Metals Company Limited

    50-60

    Xinjiang Qiya Aluminum Group

    28

    Xinjiang Jiarun Resources Holding Co., Ltd 

    30


    Xinjiang Xinfa Group plans to put about550,000t of aluminum ingot project into operation on 2015. Their capacity ofsmelting aluminum has reached 1,350,000tpy and now they keep four power generators with capacity of360,000KWH and two power generators with capacity of 1,100,000KWH on running.The company has intention to make their capacity reach about 1,900,000tpy atthe end of 2015.

    Xinjiang Tianshan Aluminum Co., Ltd plans to put 300,000-400,000t ofaluminum ingot project into operation in 2015, and the capacity would reach1.4-1.5 million tonnes at the end of 2015. Their capacity of aluminum ingotshas reached about 1.1 million tonnes till now and they hold eight powergenerators with a capacity of 350,000KWH for each on running currently.

    Xinjiang East Hope Nonferrous Metals Company Limited plans to expand itscapacity of smelting aluminum to 1.4-1.5 million tonnes at the end of 2015. Andthe company has intention to put about 500,000-600,000t of aluminum ingotprojects into operation in 2015. The capacity has reached 900,000t at the endof 2014 and there are five power generators with capacity of 350,000KWH onrunning.

    Xinjiang Qiya Group designs to put about 280,000t ofaluminum ingot project into operation in 2015, and the plant is running at thecapacity of 560,000tpy. Currently, there are three power generators with a capacity of360,000KWH for each on running.

     

     