Jinpu Titanium: Jinpu New Energy Battery Material Integration Project goes into formal construction
2022-10-10 11:23:22 [Print]
Jinpu Titanium announced recently that the Jinpu New Energy Battery Material Integration Project went into formal construction on September 29th
The project will be constructed in three phases and the construction period is expected to last from September 2022 to December 2027. The phase one project, which is planned to go into operation in the fourth quarter of 2023, will firstly build a 100,000tpy ferric phosphate & 300,000tpy sulfuric acid device with the investment of about RMB1 . 3 billion (USD182 . 79 million).
. Invested by Jinpu Titanium's wholly-owned subsidiary, Anhui Jinpu New Energy Technology Development Co . , Ltd . , the project will build an upstream and downstream integrated device for 200,000tpy ferric phosphate and 200,000tpy LFP as planned. The project will be constructed in three phases and the construction period is expected to last from September 2022 to December 2027. The phase one project, which is planned to go into operation in the fourth quarter of 2023, will firstly build a 100,000tpy ferric phosphate & 300,000tpy sulfuric acid device with the investment of about RMB1 . 3 billion (USD182 . 79 million).