• Copper Conc. TC 25%min CIF China(-1)  06-17|Silicon Metal 98.5%min Delivered US(0.05)  06-17|Selenium Powder 99.9%min Delivered China(5)  06-17|Ammonium Metavanadate 98%min EXW China(2000)  06-17|Coal Tar Pitch Coking Value 53%min EXW China(-120)  06-17|Ferro-gadolinium Gd 73% EXW China(4000)  06-17|Gadolinium Oxide 99.5%min EXW China(4000)  06-17|Ferro-silicon 75%min In warehouse Pittsburgh(-0.03)  06-17|Selenium Dioxide 98%min Delivered China(3)  06-17|PrNd Mischmetal Pr 25%, Nd 75% EXW China(10000)  06-17|Neodymium Metal 99%min EXW China(10000)  06-17|PrNd Oxide Pr6O11 25%, Nd2O3 75% EXW China(8000)  06-17|Neodymium Oxide 99.5%min EXW China(8000)  06-17|Zinc Conc. TC 50% CIF China(-0.6)  06-17
  • CNMC provides updates on overseas copper projects

    2020-03-25 15:19:29   [Print]
    China Nonferrous Metal Mining (Group) Co.Asian Metal Copyright .Asian Metal Copyright, Ltd.Asian Metal Copyright The project has a construction period of about 21 months and a service life of nine years.Asian Metal Copyright (CNMC) on March 23 provided updates on overseas copper projects for which the company raised supporting funds through non-public issuance.

    Construction of Kambove Hydrometallurgical Copper Project started on January 14, 2020 and has been ongoing in an orderly way, with trial production projected to begin in July 2021 and formal production in late October. The project has a construction period of about 21 months and a service life of nine years.

    Lualaba Copper Project commenced trial production in November 2019 and produced the first batch of up-to-standard blister copper product, with formal production started in January 2020. As of March 19, 2020, Lualaba Copper Smelter, the owner of the project, has produced about 12,000t of blister copper, 33,000t of sulfuric acid, and 376.Asian Metal Copyright Lualaba Copper Project commenced trial production in November 2019 and produced the first batch of up-to-standardblister copper product, with formal production started in January 2020.Asian Metal Copyright5t of sulfur dioxide liquid.Asian Metal Copyright CNMC on March 23 provided updates on overseas copper projects for which the company raised supporting funds through non-public issuance.Asian Metal Copyright Up to March 20, the smelter has purchased, or on an OEM basis, about 32,000t of copper metal in concentrate.

    Chambishi Southeast Orebody Exploration and Construction Project has basically finished cold commissioning which commenced in August 2018 and is on track to start production formally in April 2020. So far, the south and north parts of the project have been well-equipped with mining facilities and fully staffed with Zambian workers.Asian Metal Copyright CNMC on March 23 provided updates on overseas copper projects for which the company raised supporting funds through non-public issuance.Asian Metal Copyright The current mining capacity is about 3,000t per day and the concentration plant has reached targeted production capacity.Asian Metal Copyright So far, the south and north parts of the project have been well-equipped with mining facilities and fully staffed with Zambian workers.Asian Metal Copyright The southeast orebody would ramp up production further in Q2 2020 and is projected to reach production capacity of 10,000tpd in Q4 2020.

    .Asian Metal Copyright, LtdAsian Metal Copyright
    Copper Conc. TC 25%min CIF China
    Unit:USD/mt
    China copper concentrate producers' suspension number statistics by province by month
    Unit: pcs
      Copyright © Asian Metal Ltd All rights reserved.