• Tungsten APT 88.5%min FOB Chinaup(20)  09-19|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinadown(-12)  09-19|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinadown(-12)  09-19|Spodumene Li2O 5%min In port Chinaup(30)  09-19|Tungsten Ore WO3 50%min FOB Africaup(13)  09-19|Antimony Trioxide 99.5%min In warehouse Rotterdamdown(-1.3)  09-19|Tungsten APT 88.5%min In warehouse Rotterdamup(15)  09-19|Praseodymium Oxide 99.5%min FOB Chinaup(2500)  09-19|Tungsten Oxide WO3 99.95%min FOB Chinaup(15)  09-19|Neodymium Oxide 99.5%min FOB Chinaup(2500)  09-19|Tungsten Scrap THA 90%min Ex-VAT Delivered Chinadown(-10)  09-19|Ferro-silicon 75%min In warehouse Pittsburghdown(-0.03)  09-19|Spodumene Li2O 3%min In port Chinaup(20)  09-19|Bismuth Ingot 99.99%min EXW Chinaup(3000)  09-19
  • Eskom to fix design flaws at mammoth coal plants

    2020-05-12 14:56:01   [Print]
    South African state utility Eskom plans to correct design defects at all units of its mammoth Medupi and Kusile coal-fired power stations, it said on Monday, after completing modifications on one of the plants' units.

    Medupi and Kusile have been beset by faults and delays and are a major reason why Eskom is struggling with around 450 billion rand ($24.5 billion) of debt.

    Eskom said in a statement that modifications at Medupi Unit 3 had gone smoothly, with the unit reaching its full generation capacity of roughly 800 megawatts (MW) after returning to service. It said it would start making similar design changes, which are partly aimed at solving boiler problems, on Medupi's other units over the remainder of the year.

    Once the work on Medupi is complete, Eskom will fix flaws at sister plant Kusile, Eskom spokesman Sikonathi Mantshantsha said.

    With a capacity of 4,800 MW each, Medupi and Kusile will be among the largest coal power stations in the world when complete.