• Copper Conc. 25%min CIF China TCdown(-10)  08-14|Tungsten APT 88.5%min FOB Chinaup(50)  08-14|Tungsten Oxide WO3 99.95%min FOB Chinaup(50)  08-14|Ferro-molybdenum 60%min IW Russiaup(90)  08-14|Erbium Oxide 99.5%min FOB Chinaup(2.5)  08-14|Erbium Oxide 99.5%min IW Rotterdamup(2.5)  08-14|Tungsten Bar W-4 99.9%min FOB Chinadown(-5)  08-14|Tungsten Ore WO3 55%min EXW Chinaup(10000)  08-14|Tungsten Ore WO3 50%min FOB Africaup(50)  08-14|Titanium Dioxide Rutile, 93%min FOB Chinadown(-50)  08-14|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinadown(-30)  08-14|Strontium Metal 99%min FOB Chinaup(250)  08-14|Arsenic Trioxide 99%min EXW China down(-30)  08-14|Arsenic Trioxide 99%min FOB China down(-5)  08-14
  • Aurubis sees stable annual year after smelter maintenance

    2020-02-14 08:59:31   [Print]
    Aurubis AG, Europe's largest copper producer, on Thursday maintained its forecast of a stable financial year, although a scheduled maintenance shutdown at its main smelter hit its first-quarter numbers.

    Operating earnings before taxes (EBT) in the first quarter of its 2019/20 fiscal year ended Dec. 31 dropped to 31 million euros ($33.Asian Metal CopyrightAurubis AG, Europe's largest copper producer, on Thursday maintained its forecast of a stable financial year, although a scheduled maintenance shutdown at its main smelter hit its first-quarter numbers.Asian Metal Copyright69 million) from 40 million euros a year earlier.

    Last year, Aurubis had flagged that a planned maintenance shutdown at the group's main production plant in Hamburg last October and November was likely to have an impact of nearly 34 million euros on its first-quarter results.

    "We successfully carried out the maintenance shutdown in Hamburg in the planned timeframe and budget," said Aurubis CEO Roland Harings. "All of the planned investments and measures were accomplished.Asian Metal Copyright Aurubis repeated that it expects full-year operating EBT of between 185 million and 250 million euros and an operating ROCE return on capital employed of between 8% and 11%.Asian Metal Copyright We, therefore, expect a considerable improvement in plant availability and a higher concentrate throughput," Harings said, adding the outlook for the current fiscal year is unchanged.

    Aurubis repeated that it expects full-year operating EBT of between 185 million and 250 million euros and an operating ROCE (return on capital employed) of between 8% and 11%.

    The copper producer said its Luenen smelter in central Germany will undergo scheduled maintenance shutdowns in April and September, which will have an impact of an estimated 11 million euros on its operating EBT.

    Aurubis said it expects a good supply of copper concentrate (ore) in the new year, but with low treatment and refining charges (TC/RCs).

    .Asian Metal Copyright Aurubis said it expects a good supply of copper concentrate ore in the new year, but with low treatment and refining charges TCRCsAsian Metal Copyright
    Copper Conc. 20%min Delivered China
    Unit:RMB/mmt
    Copper Conc. 20%min Delivered China RMB/mmt
    China's copper rod producers' sales volume statistics by province by month
    Unit: mt
      Copyright © Asian Metal Ltd All rights reserved.