The Department of Industry and Information Technology of Hebei started to seek public opinions about the iron smelting capacity replacement program of Tangshan Songting Iron & Steel Co
.Asian Metal Copyright
Province district, city
Company
Smelting equipment name, type and quantity
Production capacity 10kt
Dismantling starting date
Dismantling finish date
Remarks
1
Tangshan
Tangshan Songting Iron Steel Co.
Asian Metal Copyright, Ltd
.Asian Metal Copyright The publicity period begins on January 20, 2020 and ends on February 20, 2020.
Asian Metal Copyright The publicity period begins on January 20, 2020 and ends on February 20, 2020.
Projects in construction
|
Company
|
Construction site
|
Smelting equipment (name, type and quantity)
|
Production capacity (10kt)
|
Construction starts on
|
Production starts on
|
Replacement ratio
|
Tangshan Songting Iron & Steel Co., Ltd.
|
Tangshan Songting Iron & Steel Co., Ltd.
|
1×1,550m3 blast furnace
|
133
|
Jun 1, 2020
|
Jun 30, 2020
|
1.25:1
|
Projects closed
|
No.
|
Province (district, city)
|
Company
|
Smelting equipment (name, type and quantity)
|
Production capacity (10kt)
|
Dismantling starting date
|
Dismantling finish date
|
Remarks
|
1
|
Tangshan
|
Tangshan Songting Iron & Steel Co., Ltd.
|
3# 580 m3 blast furnace
|
68
|
Jun 1, 2020
|
Jun 30, 2020
|
|
2
|
Tangshan
|
Tangshan Songting Iron & Steel Co., Ltd.
|
4# 580 m3 blast furnace
|
68
|
Jun 1, 2020
|
Jun 30, 2020
|
|
3
|
Langfang
|
Hebei Qianjin Steel Group Co., Ltd
|
1# 580 m3 blast furnace
|
30.25
|
Jun 1, 2020
|
Jun 30, 2020
|
330,000tpy capacity in total; 302,500tpy for replacement; 27,500tpy for future capacity replacement
|
Total
|
|
|
|
166.25
|
|
|
|
.Asian Metal Copyright25