• Lead Conc. Pb 50%min, Ag 1,000g/dt max EXW China TCdown(-100)  09-24|Iron Ore Fine Australian 58%min In port Chinadown(-20)  09-24|Iron Ore Fine 65%min Ex-VAT EXW Shanxidown(-20)  09-24|Iron Ore Fine Australian 62%min In port Chinadown(-20)  09-24|Cobalt Sulfate 20.5%min Delivered Chinadown(-1500)  09-24|Coal Tar Pitch Coking Value 56%min EXW Chinadown(-200)  09-24|Chromic Anhydride 99.8%min EXW Chinaup(500)  09-24|Spodumene Li2O 3%min In port Chinadown(-50)  09-24|Iron Ore Fine 65%min EXW Liaoningdown(-20)  09-24|HR Coil IS2062 3.0mm IW Mumbaiup(1500)  09-24|Spodumene Li2O 6%min CIF Chinadown(-50)  09-24|Lithium Manganate Mn 58% Delivered Chinadown(-1000)  09-24|Iron Ore Lump Australian 62%min In port Chinadown(-20)  09-24|Iron Ore Fine Brazilian 65%min In port Chinadown(-20)  09-24
  • Capacity replacement scheme of Chifeng Zhongtang Special Steel project in public

    2020-01-21 17:26:25   [Print]
    On January 17, the Department of Industry and Information Technology of Inner Mongolia Autonomous Region publicized the capacity replacement plan of 2.Asian Metal Copyright, Ltd.Asian Metal Copyright7 million tpy of fine steel project of Chifeng Zhongtang Special Steel Co.Asian Metal Copyright1 .Asian Metal Copyright, Ltd.Asian Metal CopyrightOn January 17, the Department of Industry and Information Technology of Inner Mongolia Autonomous Region publicized the capacity replacement plan of 2.Asian Metal Copyright The publicity period is five working days from the publicity date.

    Construction project situation

    Enterprise Name

    Construction site

    Name, model and quantity of smelting equipment

    Capacity conversion

    (10,000t)

    Planned commencement time

    Planned

    production

    time

    Replacement proportion

    Chifeng Zhongtang Special Steel Co., Ltd.

    Ningcheng, Chifeng

    Two blast furnaces of 1580 cubic meters

    2.74 million ton

    April 1, 2020

    March 30, 2022

    1.0004:1

    Two 120 ton converters

    2.70 million ton

     

     

    1.0004:1

    Project exit situation

    No.

    Province (District, city)

    Enterprisename

    Name, Model and Quantity of smelting equipment

    Capacity conversion

    (10,000t)

    Removal starting time

    Removal in place time

    Remarks

    1

    Tangshan, Hebei

    Tangshan Jinma Steel Group

    3 × 500m3 blast furnace

    59

    Before the project put into production

    Before the project put into production

     

    2

     

     

    1 × 1080m3 blast furnace

    104

     

     

    Of this total, 1.111 million tons was used to reduce the production capacity of the project, and the remaining 109,000 tons of production capacity was used by Chifeng Zhongtang Special Steel Co.Asian Metal Copyright Total Ironmaking 285 Steelmaking 270.Asian Metal Copyright, Ltd.Asian Metal Copyright0004:1 Project exit situation No.Asian Metal Copyright for other purposes.

    3

     

     

    2 × 1350m3 blast furnace

    122

     

     

    4

    Tangshan, Hebei

    Tangshan Jinma Steel Group

    Two 120t converter    270

     

     

     

     

    Ulanhot,

    Inner Mongolia

    Wulanhaote Steel Co., Ltd.

    Two 35t

    converter

    0.1

    This capacity belongs to the capacity reserved by the demolished equipment after the completion of replacement in the announcement of the Department of industry and information technology of Inner Mongolia Autonomous Region on the steel capacity replacement plan of Ulanhot Steel Co., Ltd.Asian Metal CopyrightOn January 17, the Department of Industry and Information Technology of Inner Mongolia Autonomous Region publicized the capacity replacement plan of 2.Asian Metal Copyright (Neigong Xinyuan Gong Zi [2019] No.Asian Metal Copyright74 million ton April 1, 2020 March 30, 2022 1.Asian Metal Copyright 136).   

    This capacity belongs to the capacity reserved by the demolished equipment after the completion of replacement in the announcement of the Department of industry and information technology of Inner Mongolia Autonomous Region on the steel capacity replacement plan of Ulanhot Steel Co., Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright (Neigong Xinyuan Gong Zi [2019] No.Asian Metal Copyright for other purposes.Asian Metal Copyright 136).  

     

     

    Total

    /

    /

    /

    Ironmaking

    285

     /

     /

     /

    Steelmaking

    270.1

     

     




    .Asian Metal Copyright 3 2 × 1350m3 blast furnace 122 4 Tangshan,Hebei Tangshan Jinma Steel Group Two 120t converter 270 Ulanhot, Inner Mongolia Wulanhaote Steel CoAsian Metal Copyright