• Tungsten APT 88.5%min FOB Chinaup(20)  09-19|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinadown(-12)  09-19|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinadown(-12)  09-19|Spodumene Li2O 5%min In port Chinaup(30)  09-19|Tungsten Ore WO3 50%min FOB Africaup(13)  09-19|Antimony Trioxide 99.5%min In warehouse Rotterdamdown(-1.3)  09-19|Tungsten APT 88.5%min In warehouse Rotterdamup(15)  09-19|Praseodymium Oxide 99.5%min FOB Chinaup(2500)  09-19|Tungsten Oxide WO3 99.95%min FOB Chinaup(15)  09-19|Neodymium Oxide 99.5%min FOB Chinaup(2500)  09-19|Tungsten Scrap THA 90%min Ex-VAT Delivered Chinadown(-10)  09-19|Ferro-silicon 75%min In warehouse Pittsburghdown(-0.03)  09-19|Spodumene Li2O 3%min In port Chinaup(20)  09-19|Bismuth Ingot 99.99%min EXW Chinaup(3000)  09-19
  • Capacity transfer scheme for construction project of Guangxi Chiji Iron and Steel

    2020-01-21 15:44:45   [Print]
    On January 14, Department of Industry and Information Technology of Guangxi sought public opinions on the capacity transfer scheme for construction project of Wuzhou Guangxi Chiji Iron and Steel Co.Asian Metal CopyrightOn January 14, Department of Industry and Information Technology of Guangxi sought public opinions on the capacity transfer scheme for construction project of Wuzhou Guangxi Chiji Iron and Steel Co.Asian Metal Copyright, Ltd.Asian Metal Copyright25 million tons for technology upgrading projects of Guangxi Shenglong Metallurgy Co.Asian Metal Copyright; the publication period is from January 14, 2020 to January 21, 2020.

    Construction Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Wuzhou Guangxi Chiji Iron and Steel Co., Ltd.

    Wuzhou, Guangxi

    3 blast furnaces of 2,060 cubic meters; 3 converters of 150t. (This transfer cannot meet the need of the proposed construction project.Asian Metal Copyright 2 Guangxi Guangxi Shenglong Metallurgy Co.Asian Metal Copyright It can be recorded and start construction when the iron-making capacity reaches 525.Asian Metal Copyright, Ltd.Asian Metal Copyright3 and steel-making capacity reaches 480.)

    525.3 of iron-making; 480 of steel-making

    May 2020

    May 2021

    Transfer based on the requirements of notice for capacity transfer implementation in iron, steel, cement and glass industry issued by MIIT (No. [2017]337.)

    Cancelled Projects

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Guangxi

    Guangxi Shenglong Metallurgy Co., Ltd.

    2 blast furnaces of 450 cubic meters and 2 of 600 cubic meters

    175 of iron-making

    Before operation of new project

    Before operation of new project

    The approved capacity is 3 million tons based on 2 blast furnaces of 450 cubic meters and 2 of 600 cubic meters, including 1.25 million tons for technology upgrading projects of Guangxi Shenglong Metallurgy Co.Asian Metal Copyright 2 Guangxi Guangxi Shenglong Metallurgy Co.Asian Metal Copyright, Ltd.Asian Metal Copyright25 million tons for technology upgrading projects of Guangxi Shenglong Metallurgy Co.Asian Metal Copyright in future and the rest of 1.Asian Metal Copyright; the publication period is from January 14, 2020 to January 21, 2020.Asian Metal Copyright75 million tons transferred to Wuzhou Guangxi Chiji Iron and Steel Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.

    2

    Guangxi

    Guangxi Shenglong Metallurgy Co., Ltd.

    2 converters of 60t and 3 of 80t

    31 of steel-making

    Before operation of new project

    Before operation of new project

    The approved capacity is 6 million tons based on 2 converters of 60t and 3 of 80t, including 5.69 million tons for technology upgrading projects of Guangxi Shenglong Metallurgy Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright in future and the rest of 310,000t transferred to Wuzhou Guangxi Chiji Iron and Steel Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.

    Total

    The capacity of this scheme for transfer contains 1.75 million tons of iron-making and 310,000t of steel-making.Asian Metal Copyright Construction Project Company Location Facilities Transfer capacity 10kt Proposed construction date Proposed operation date Transfer ratio Wuzhou Guangxi Chiji Iron and Steel Co.Asian Metal Copyright The rest capacity that the project need will be released after the company purchases legal other capacities.


    .Asian Metal Copyright Construction Project Company Location Facilities Transfer capacity 10kt Proposed construction date Proposed operation date Transfer ratio Wuzhou Guangxi Chiji Iron and Steel CoAsian Metal Copyright