• Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max Delivered Chinadown(-5000)  04-21|Tungsten Scrap THA 90%min Ex-VAT Delivered Chinadown(-30)  04-21|NdFeB Sintered Rough N35 Block EXW Chinaup(5)  04-21|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinadown(-25)  04-21|Antimony Trioxide 99.5%min IW Baltimoredown(-0.4)  04-21|Praseodymium Metal 99.5%min FOB Chinaup(4)  04-21|Antimony Ingot 99.65%min IW Baltimoredown(-0.4)  04-21|Cerium Metal 99%min FOB Chinaup(0.12)  04-21|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinadown(-25)  04-21|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max FOB Chinadown(-0.5)  04-21|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max Delivered South Koreadown(-0.5)  04-21|Zirconium Carbonate Zr(Hf)O2 40%min, Cl 0.2%max EXW Chinaup(500)  04-21|Antimony Trioxide 99.5%min IW Rotterdamdown(-0.6)  04-21|Zirconium Carbonate Zr(Hf)O2 40%min, Cl 50ppm max EXW Chinaup(500)  04-21
  • Capacity transfer scheme for construction project of Henan Jiyuan Iron and Steel

    2020-01-16 16:03:18   [Print]
    On January 13, 2020, Department of Industry and Information Technology of Henan sought public opinions on the capacity transfer scheme for construction project of Henan Jiyuan Iron and Steel (Group) Co.Asian Metal Copyright60 million tons for construction project, a reduction of 5,000t and the rest of 5,000t for self-use of the company.Asian Metal Copyright, Ltd.Asian Metal Copyright Construction Project Company Location Facilities Transfer capacity 10kt Proposed construction date Proposed operation date Transfer ratio Henan Jiyuan Iron and Steel Group Co.Asian Metal Copyright; the publication period is from January 13, 2020 to February 13, 2020.

    Construction Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Henan Jiyuan Iron and Steel (Group) Co., Ltd.

    Existing plant area

    2 blast furnaces of 1,300 cubic meters

    238.2

    One blast furnace in 2020, one in 2022

    One blast furnace in 2021, one in 2023

    Reduction of 5,000t

    1 converter of 104t

    119

    2022

    2023

    Reduction of 5,000t

    1 alloy steel electric furnace of 55t

    41

    2022

    2023

    Cancelled Projects

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Jiyuan, Henan

    Henan Jiyuan Iron and Steel (Group) Co., Ltd.

    4 blast furnaces of 508 cubic meters

    239.2

    Two blast furnaces in 2021, the rest in 2023

    Two blast furnaces in 2021, the rest in 2023

    Transferred capacity contains 2.392 million tons of iron-making capacity in total, including 2.Asian Metal Copyright382 million tons for construction project, a reduction of 5,000t and the rest of 5,000t for self-use of the company.Asian Metal Copyright382 million tons for construction project, a reduction of 5,000t and the rest of 5,000t for self-use of the company.

    2

    Jiyuan, Henan

    Henan Jiyuan Iron and Steel (Group) Co., Ltd.

    1 converter of 50t

    76

    2023

    2023

    Transferred capacity contains 1.61 million tons of steel-making capacity in total, including 1.Asian Metal Copyright382 million tons for construction project, a reduction of 5,000t and the rest of 5,000t for self-use of the company.Asian Metal Copyright60 million tons for construction project, a reduction of 5,000t and the rest of 5,000t for self-use of the company.

    3

    Jiyuan, Henan

    Henan Jiyuan Iron and Steel (Group) Co., Ltd.

    1 converter of 60t

    85

    2023

    2023

    Total

    /

    /

    /

    239.2 of iron-making; 161 of steel-making

    /

    /

    /



    .Asian Metal Copyright; the publication period is from January 13, 2020 to February 13, 2020Asian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.