• Tungsten Ore WO3 55%min EXW Chinaup(15000)  01-19|Tungsten APT 88.5%min In warehouse Rotterdamup(30)  01-19|Tungsten Carbide 99.8%min 2.5-7.0μm EXW Chinaup(34)  01-19|Tungsten Ore WO3 65%min EXW Chinaup(15000)  01-19|Tungsten Powder 99.95%min 2.5-7.0μm EXW Chinaup(35)  01-19|Tungsten Bar W-4 99.9%min EXW Chinaup(35)  01-19|Ferro-tungsten 75%min In warehouse Rotterdamup(4)  01-19|Lithium Carbonate 99.2%min Delivered Chinadown(-4600)  01-19|Lithium Carbonate 99.5%min Delivered Chinadown(-4600)  01-19|Cobalt Metal 99.8%min Delivered Chinadown(-13)  01-19|Ferro-tungsten 75%min EXW Chinaup(20000)  01-19|Tungsten Carbide 99.8%min 2.5-7.0μm FOB Chinaup(5)  01-19|Tungsten APT 88.5%min EXW Chinaup(20000)  01-19|Molybdenum Scrap Wire 99.95%min Ex-VAT EXW Chinaup(10)  01-19
  • Capacity transfer scheme for steel-making construction project of Hebei Xinda Iron and Steel Group

    2020-01-15 17:02:57   [Print]
    On January 13, 2020, Department of Industry and Information Technology of Hebei sought public opinions on the capacity transfer scheme for steel-making construction project of Hebei Xinda Iron and Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright75 Before operation of new project Before operation of new project The purchased capacity was 610,000t in the contract.Asian Metal Copyright (the announcement of capacity transfer scheme for Hebei Xinda Iron and Steel Co.Asian Metal Copyright Total 143.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright that was released on December 3, 2019 was abolished.Asian Metal Copyright75 .Asian Metal Copyright); the publication period is from January 13, 2020 to February 12, 2020.

    Construction of Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Hebei Xinda Iron and Steel Group Co., Ltd.

    Plant area of Hebei Xinda Iron and Steel Group

    1 converter of 100t

    115

    October 2019

    June 2020

    1.25:1

    Cancelled Projects

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Tangshan

    Hebei Xinda Iron and Steel Group Co., Ltd.

    2# 80t converter

    15

    Before operation of new project

    Before operation of new project

    The rest of 850,000t capacity will be used in capacity transfer in future

    2

    Tangshan

    Hebei Xinda Iron and Steel Group Co., Ltd.

    3# 80t converter

    100

    Before operation of new project

    Before operation of new project

     

    7

    Langfang

    Bazhou Xinli Iron and Steel Co., Ltd.

    2# 120t converter

    28.75

    Before operation of new project

    Before operation of new project

    The purchased capacity was 610,000t in the contract. After correction, the capacity is 588,200t.Asian Metal Copyright that was released on December 3, 2019 was abolished.Asian Metal Copyright The rest of 300,700t will be used in capacity transfer in future.

    Total

     

     

     

    143.75

     

     

     