• Selenium Dioxide 98%min Delivered Chinadown(-5)  05-29|Tungsten Scrap Grinding Swarf W 70%min, Co 5%min Ex-VAT Delivered Chinaup(180)  05-29|Ferro-tungsten 75%min FOB Chinaup(5)  05-29|Chrome Lump S.A. 38%min In port Chinadown(-1.5)  05-29|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinaup(15)  05-29|Ferro-tungsten 75%min EXW Chinaup(20000)  05-29|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinaup(15)  05-29|Tungsten Ore WO3 55%min EXW Chinaup(10000)  05-29|Tungsten APT 88.5%min FOB Chinaup(40)  05-29|Tungsten Scrap THA 90%min Ex-VAT Delivered Chinaup(15)  05-29|Tungsten APT 88.5%min EXW Chinaup(15000)  05-29|Met. Coke A 13%max, S 0.7%max EXW Shanxiup(40)  05-29|Ferro-chrome Indian Cr 58%min, C 8%max In port Chinadown(-200)  05-29|Selenium Powder 99.9%min Delivered Chinadown(-5)  05-29
  • Shanxi Hongda Steel Group implements capacity reduction replacement plan

    2020-01-10 18:01:48   [Print]
    On January 9, the Department of Industry and Information Technology of Shanxi announced the capacity reduction replacement plan of Shanxi Hongda Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.

    Construction projects

    Enterprise name

    Construction address

    Equipment name, model and quantity

    Conversion capacity (10000 tons)

    Planned start time

    Planned production time

    Replacement proportion

    Shanxi Hongda iron and Steel Group

    Xiaozhang village, Senglou Town, Hejin City, Yuncheng City, Shanxi Province

    2 × 100t converter

    230

    October 2019

    December 2020

    1.008:1

    Exit capacity

    No.

    Province(district)

    Enterprise Name

    Equipment name, model and quantity conversion capacity (10000 tons)

    Conversion capacity (10,000 tons)

    Time to start demolition

    Time to dismantle in place

    Others

    1

    Yuncheng, Shanxi

    Shanxi Hongda iron and Steel Group Co., Ltd.

    1 × 60t converter

    85

      three months before 2 × 100t converter  was put into operation

    before 2 × 100t converter  was put into operation

    After a reduction of 1.008: 1, the actual capacity will be reduced by 20,000 tons, and the remaining 30,000 tons will be used for other capacity replacement projects.

    1 × 120t converter

    135

    2

    Jincheng, Shanxi

    Jincheng Fusheng Steel Co., Ltd

    1 × 100t converter replace remaining capacity

    15