On January 9, the Department of Industry and Information Technology of Shanxi announced the capacity reduction replacement plan of Shanxi Hongda Steel Group Co
.Asian Metal Copyright, Ltd.
Asian Metal Copyright, Ltd.
Construction projects
|
Enterprise name
|
Construction address
|
Equipment name, model and quantity
|
Conversion capacity (10000 tons)
|
Planned start time
|
Planned production time
|
Replacement proportion
|
Shanxi Hongda iron and Steel Group
|
Xiaozhang village, Senglou Town, Hejin City, Yuncheng City, Shanxi Province
|
2 × 100t converter
|
230
|
October 2019
|
December 2020
|
1.008:1
|
Exit capacity
|
No.
|
Province(district)
|
Enterprise Name
|
Equipment name, model and quantity conversion capacity (10000 tons)
|
Conversion capacity (10,000 tons)
|
Time to start demolition
|
Time to dismantle in place
|
Others
|
1
|
Yuncheng, Shanxi
|
Shanxi Hongda iron and Steel Group Co., Ltd.
|
1 × 60t converter
|
85
|
three months before 2 × 100t converter was put into operation
|
before 2 × 100t converter was put into operation
|
After a reduction of 1.008: 1, the actual capacity will be reduced by 20,000 tons, and the remaining 30,000 tons will be used for other capacity replacement projects.
|
1 × 120t converter
|
135
|
2
|
Jincheng, Shanxi
|
Jincheng Fusheng Steel Co., Ltd
|
1 × 100t converter replace remaining capacity
|
15
|
.Asian Metal Copyright
1 × 60t converter
85
three months before 2 × 100t converter was put into operation
before 2 × 100t converter was put into operation
After a reduction of 1Asian Metal Copyright