• Copper Conc. TC 25%min CIF Chinadown(-3)  07-11|Polysilicon 9N Delivered Chinaup(2)  07-11|Silicon Metal 4-4-1 Delivered Chinaup(300)  07-11|Silicon Metal 4-2-1 Delivered Chinaup(300)  07-11|Molybdenum Scrap Wire 99.95%min Ex-VAT EXW Chinaup(10)  07-11|Erbium Oxide 99.5%min EXW Chinaup(9)  07-11|Antimony Ingot 99.65%min In port Indiaup(140)  07-11|Ferro-silicon 75%min In warehouse Pittsburghdown(-0.03)  07-11|Iron Ore Fine Australian 62%min In port Chinaup(20)  07-11|Dysprosium Oxide 99.5%min EXW Chinaup(45)  07-11|Molybdenum Scrap Cutting 99.95%min Ex-VAT EXW Chinaup(10)  07-11|Iron Ore Fine Australian 62%min CNF Chinaup(2.5)  07-11|Iron Ore Fine Brazilian 65%min In port Chinaup(20)  07-11|Rhenium APR 99.99%min EXW Chinaup(200)  07-11
  • Capacity transfer scheme of Rizhao Steel

    2019-12-13 15:37:10   [Print]
    On December 12, Department of Industry and Information Technology of Shandong sought public opinions on the capacity transfer scheme of Rizhao Steel Holding Group Co.Asian Metal Copyright 1 blast furnace of 630 cubic meters; 1 converter of 40t 73 of iron-making; 60 of steel-making Before the construction project start Before the construction project start This reduction transfer consists of 1,000t of iron-making and 1,000t of steel-making.Asian Metal Copyright, Ltd.Asian Metal Copyright The rest of 430,500t of iron-making and 358,000t of steel-making will be used in future capacity transfer.Asian Metal Copyright; the publication period is from December 12, 2019 to January 9, 2020.

    Construction of Project

    Company

    Location

    Facility

    Capacity (10kt)

    Proposed building time

    Proposed start time

    Transfer ratio

    Rizhao Steel Holding Group Co., Ltd.

    Lanshan District, Rizhao

    1 blast furnace of 300 cubic meters; 2 converters of 120t

    250 of iron-making; 270of steel-making

    2020

    2022

    Reduction

    Cancelled Project

    No.

    Location

    Company

    Facility

    Capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Shandong

    Zibo Qilin Fushan Iron and Steel Co., Ltd.

    1 blast furnace of 630 cubic meters; 1 converter of 40t

    73 of iron-making; 60 of steel-making

    Before the construction project start

    Before the construction project start

    This reduction transfer consists of 1,000t of iron-making and 1,000t of steel-making. The rest of 430,500t of iron-making and 358,000t of steel-making will be used in future capacity transfer.

    2

    Shandong

    Shandong Longsheng Iron and Steel Co., Ltd.

    1 blast furnace of 630 cubic meters; 1 blast furnace of 720 cubic meters; 2 converters of 65t

    151.25 of iron-making; 180 of steel-making

    Before the construction project start

    Before the construction project start

    3

    The rest of 689,000t of iron-making capacity and 659,000t of steel-making capacity of capacity transfer scheme for Rizhao Steel Holding Group Co., Ltd. that published on November 13, 2019