• NCM 523 Delivered Chinaup(2900)  10-29|NCM 613 Delivered Chinaup(2700)  10-29|Erbium Oxide 99.5%min FOB Chinaup(1.5)  10-29|Cobalt Carbonate 46%min Delivered Chinaup(5000)  10-29|Cobalt Metal 99.8%min In warehouse Rotterdamup(0.6)  10-29|Cobalt Oxide 72%min In warehouse Rotterdamup(0.9)  10-29|Sodium Pyroantimonate 58.4% Delivered Chinadown(-2000)  10-29|NCM 8312 Delivered Chinaup(3000)  10-29|Ferro-molybdenum 60%min Delivered Indiadown(-80)  10-29|Coal Tar Pitch Coking Value 56%min EXW Chinadown(-100)  10-29|Cobalt Metal 99.8%min Delivered Chinaup(10)  10-29|Ferro-molybdenum 60%min In warehouse Russiadown(-80)  10-29|Spinel SMBS 62 EXW Chinadown(-100)  10-29|Molybdenum Scrap Cutting 99.95%min Ex-VAT EXW Chinadown(-10)  10-29
  • Capacity transfer scheme of Rizhao Steel

    2019-12-13 15:37:10   [Print]
    On December 12, Department of Industry and Information Technology of Shandong sought public opinions on the capacity transfer scheme of Rizhao Steel Holding Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright; the publication period is from December 12, 2019 to January 9, 2020.

    Construction of Project

    Company

    Location

    Facility

    Capacity (10kt)

    Proposed building time

    Proposed start time

    Transfer ratio

    Rizhao Steel Holding Group Co., Ltd.

    Lanshan District, Rizhao

    1 blast furnace of 300 cubic meters; 2 converters of 120t

    250 of iron-making; 270of steel-making

    2020

    2022

    Reduction

    Cancelled Project

    No.

    Location

    Company

    Facility

    Capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Shandong

    Zibo Qilin Fushan Iron and Steel Co., Ltd.

    1 blast furnace of 630 cubic meters; 1 converter of 40t

    73 of iron-making; 60 of steel-making

    Before the construction project start

    Before the construction project start

    This reduction transfer consists of 1,000t of iron-making and 1,000t of steel-making. The rest of 430,500t of iron-making and 358,000t of steel-making will be used in future capacity transfer.

    2

    Shandong

    Shandong Longsheng Iron and Steel Co., Ltd.

    1 blast furnace of 630 cubic meters; 1 blast furnace of 720 cubic meters; 2 converters of 65t

    151.25 of iron-making; 180 of steel-making

    Before the construction project start

    Before the construction project start

    3

    The rest of 689,000t of iron-making capacity and 659,000t of steel-making capacity of capacity transfer scheme for Rizhao Steel Holding Group Co., Ltd. that published on November 13, 2019



    .Asian Metal Copyright Construction of Project Company Location Facility Capacity 10kt Proposed building time Proposed start time Transfer ratio Rizhao Steel Holding Group CoAsian Metal Copyright