• Pet Coke S 3%max EXW Chinaup(100)  09-17|Calcined Pet Coke S 3%max EXW Chinaup(100)  09-17|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinadown(-12)  09-17|Tungsten Scrap Drills 88%min Ex-VAT Delivered Chinadown(-12)  09-17|Tungsten APT 88.5%min In warehouse Rotterdamup(15)  09-17|Nickel Sulfate Ni 22%min; Co 0.05%max Delivered Chinaup(800)  09-17|Tungsten APT 88.5%min FOB Chinaup(15)  09-17|Tungsten Carbide 99.8%min 2.5-7.0μm FOB Chinaup(2.5)  09-17|Tungsten Oxide WO3 99.95%min FOB Chinaup(15)  09-17|Tungsten Scrap Anvil 90%min Ex-VAT Delivered Chinadown(-12)  09-17|Tungsten Bar W-4 99.9%min FOB Chinaup(2.5)  09-17|Bismuth Ingot 99.99%min EXW Chinaup(3000)  09-17|Cobalt Powder 99.5%min Delivered Chinaup(8)  09-17|Ferro-tungsten 75%min FOB Chinaup(2)  09-17
  • Anyang changes heavy air pollution alert level from orange to red

    2019-12-12 18:02:24   [Print]
    Henan would experience heavy air pollution from December 12 to 18, according to the local authority's prediction on December 9.Asian Metal Copyright Anyang Iron and Steel Group Corporation is required to shut down two sintering furnaces, one blast furnace, with another blast furnace preheated for 120 hours.Asian Metal Copyright In order to effectively reduce emissions of air pollutants, the office for environmental pollution prevention and control of Anyang government decided to change the heavy air pollution alert level from orange to red starting at 12:00 a.Asian Metal Copyright on December 12.Asian Metal Copyrightm.Asian Metal Copyright3 meters shall extend coking time to 36 hours, and those with height of 4.Asian Metal Copyright on December 12.

    Anyang Iron and Steel Group Corporation is required to shut down two sintering furnaces, one blast furnace, with another blast furnace preheated for 120 hours. Any abnormal operation of environmentally-unfriendly facility is strictly prohibited.Asian Metal Copyright Other steel companies in Anyang are required to shut down sintering furnaces and the running blast furnaces should be preheated for 120 hours.Asian Metal Copyright Other steel companies in Anyang are required to shut down sintering furnaces and the running blast furnaces should be preheated for 120 hours.

    For coking industries, coking furnaces with height above 4.3 meters shall extend coking time to 36 hours, and those with height of 4.Asian Metal Copyright For companies that are required to relocate from city to industrial park but fail to do so within the appointed period, they are required to suspend production starting at 12:00 a.Asian Metal Copyright3 meters shall extend coking time to 48 hours.

    For companies that are required to relocate from city to industrial park but fail to do so within the appointed period, they are required to suspend production starting at 12:00 a.m.Asian Metal Copyright Any abnormal operation of environmentally-unfriendly facility is strictly prohibited.Asian Metal Copyright on December 12.

    .Asian Metal Copyright Other steel companies in Anyang are required to shut down sintering furnaces and the running blast furnaces should be preheated for 120 hoursAsian Metal Copyright