Tiekeng Mining resumes iron concentrate production
2019-11-21 17:05:49 [Print]
On November 1, Jiangxi Xinyu Tiekeng Mining Co
On January 4, 2018, a tailings leakage occurred at No. 1 drainage well of Guishan tailings reservoirs, which caused damage to the flood drainage tunnel and production halt of iron concentrate . Tiekeng Mining carried out emergency management and then took hidden dangers treatment for tailings reservoirs for more than a year.
During the treatment, the company completed the construction of new No. 1 drainage well and the reconstruction of main tunnel on time, and passed the on-site acceptance of external experts on July 30 . On August 19, Ministry of Emergency Management of Jiangxi approved the trial operation of Tiekeng Mining.
. , Ltd . renewed two safety production licenses for Guishan tailings reservoirs and open-pit mining and got the approval from the Ministry of Emergency Management of Jiangxi . The company has produced 91,200 tons of qualified iron concentrate with a grade of 52 . 26% and a recovery rate of 58 . 11% since trial production; its sales volume of iron concentrate has reached 90,000 tons.
On January 4, 2018, a tailings leakage occurred at No. 1 drainage well of Guishan tailings reservoirs, which caused damage to the flood drainage tunnel and production halt of iron concentrate . Tiekeng Mining carried out emergency management and then took hidden dangers treatment for tailings reservoirs for more than a year.
During the treatment, the company completed the construction of new No. 1 drainage well and the reconstruction of main tunnel on time, and passed the on-site acceptance of external experts on July 30 . On August 19, Ministry of Emergency Management of Jiangxi approved the trial operation of Tiekeng Mining.