• Stainless HR Coil 201/No.1 6.0mm In warehouse Chinaup(200)  01-16|Lithium Metal 99%min Delivered Chinaup(22000)  01-16|Aluminum Fluoride 61%min EXW Chinadown(-300)  01-16|Yttrium Oxide 99.999%min EXW Chinaup(1500)  01-16|Ferro-vanadium 80%min In warehouse Pittsburghup(0.8)  01-16|Spodumene Li2O 3%min In port Chinaup(50)  01-16|Tungsten Scrap THA 90%min Ex-VAT Delivered Chinaup(20)  01-16|Lithium Metal 99.9%min Delivered Chinaup(22000)  01-16|Stainless CR Coil 201/2B 1.0mm In warehouse Chinaup(200)  01-16|Spodumene Li2O 5%min In port Chinaup(60)  01-16|Antimony Ingot 99.65%min In port Indiadown(-80)  01-16|Coking Coal A 10.5%max, S 0.8%max EXW Shanxiup(40)  01-16|Tungsten Scrap Grinding Swarf W 70%min, Co 5%min Ex-VAT Delivered Chinaup(200)  01-16|Tantalum Pentoxide 99.5%min EXW Chinaup(50)  01-16
  • Capacity transfer scheme for steel-making construction project of Lingyuan Iron and Steel

    2019-11-15 17:15:00   [Print]
    Recently, Department of Industry and Information Technology of Liaoning sought public opinions on the capacity transfer scheme for steel-making construction project of Lingyuan Iron and Steel Group Co.Asian Metal Copyright; details as follows: Construction of Project Company Location Facilities Capacity 10kt Proposed construction time Proposed operation time Transfer Ratio Lingyuan Iron and Steel Group Co.Asian Metal Copyright, Ltd.; details as follows:

    Construction of Project

    Company

    Location

    Facilities

    Capacity (10kt)

    Proposed construction time

    Proposed operation time

    Transfer Ratio

    Lingyuan Iron and Steel Group Co., Ltd.

    Lingyuan, Chaoyang, Liaoning

    1 converter of 120t

    135

    October 2020

    September 2022

    1.004:1

    Cancelled Project

    No.

    Province

    Company

    Facilities

    Capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Lingyuan, Chaoyang, Liaoning

    Lingyuan Iron and Steel Group Co., Ltd.

    3 converters of 35t

    165

    August 2022

    September 2022

    5,000t of capacity was reduced and 295kt will be left for use.

    Total

    /

    /

    /

    165

    /

    /

    /



    .Asian Metal Copyright Province Company Facilities Capacity 10kt Demolition start date Demolition completion date Note 1 Lingyuan, Chaoyang, Liaoning Lingyuan Iron and Steel Group CoAsian Metal Copyright