• Mercury Metal 99.9%min Ex-VAT EXW Chinadown(-110)  06-10|Lithium Iron Phosphate Li 3.9%min Delivered Chinadown(-2000)  06-10|Monazite TREO 54%min In port Chinadown(-1700)  06-10|Tungsten Scrap Grinding Swarf W 70%min, Co 5%min Ex-VAT Delivered Chinaup(200)  06-10|Tin Conc. Burmese 20%min IW MengAdown(-10000)  06-10|Tin Conc. Burmese 30%min IW MengAdown(-10000)  06-10|Germanium Dioxide 99.99%min EXW Chinaup(400)  06-10|Ferro-tungsten 75%min FOB Chinaup(5)  06-10|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinaup(40)  06-10|Tin Conc. 60%min Delivered Chinadown(-10000)  06-10|Tin Ingot 99.95%min EXW Chinadown(-10000)  06-10|Ferro-tungsten 75%min EXW Chinaup(20000)  06-10|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinaup(15)  06-10|Germanium Metal 99.99%min EXW Chinaup(500)  06-10
  • Capacity transfer scheme for steel-making construction project of Lingyuan Iron and Steel

    2019-11-15 17:15:00   [Print]
    Recently, Department of Industry and Information Technology of Liaoning sought public opinions on the capacity transfer scheme for steel-making construction project of Lingyuan Iron and Steel Group Co.Asian Metal CopyrightRecently, Department of Industry and Information Technology of Liaoning sought public opinions on the capacity transfer scheme for steel-making construction project of Lingyuan Iron and Steel Group Co.Asian Metal Copyright, Ltd.; details as follows:

    Construction of Project

    Company

    Location

    Facilities

    Capacity (10kt)

    Proposed construction time

    Proposed operation time

    Transfer Ratio

    Lingyuan Iron and Steel Group Co., Ltd.

    Lingyuan, Chaoyang, Liaoning

    1 converter of 120t

    135

    October 2020

    September 2022

    1.004:1

    Cancelled Project

    No.

    Province

    Company

    Facilities

    Capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Lingyuan, Chaoyang, Liaoning

    Lingyuan Iron and Steel Group Co., Ltd.

    3 converters of 35t

    165

    August 2022

    September 2022

    5,000t of capacity was reduced and 295kt will be left for use.

    Total

    /

    /

    /

    165

    /

    /

    /