• Ferro-tungsten 75%min IW Rotterdamdown(-5)  10-30|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max FOB Chinadown(-0.4)  10-30|Tin Conc. Burmese 20%min IW MengAdown(-10000)  10-30|Tin Conc. Burmese 30%min IW MengAdown(-10000)  10-30|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max Delivered South Koreadown(-0.4)  10-30|Lanthanum Oxide 99.999%min EXW Chinadown(-1300)  10-30|Ytterbium Oxide 99.99%min EXW Chinaup(4)  10-30|Lithium Carbonate 99.5%min Delivered EUdown(-0.4)  10-30|Lithium Carbonate 99.5%min CIF Chinadown(-0.4)  10-30|Tin Conc. 60%min Delivered Chinadown(-10000)  10-30|Spodumene Li2O 5%min In port Chinadown(-50)  10-30|Tin Ingot 99.95%min EXW Chinadown(-10000)  10-30|Lithium Carbonate 99.5%min Delivered USdown(-0.4)  10-30|Flake Graphite +195 FOB Africaup(20)  10-30
  • Capacity transfer scheme of Tangshan Jinma Steel Group

    2019-11-12 13:44:37   [Print]
    On November 8, Department of Industry and Information Technology of Hebei sought public opinions on the capacity transfer scheme of Tangshan Jinma Steel Group Co.Asian Metal CopyrightOn November 8, Department of Industry and Information Technology of Hebei sought public opinions on the capacity transfer scheme of Tangshan Jinma Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright; the publication period is from November 8, 2019 to December 5, 2019.Asian Metal Copyright .Asian Metal Copyright At the same time, the department announced to cancel the announcement for capacity transfer scheme of construction projects of Tangshan Jinma Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright Ningcheng, Chifeng High-quality steel project of Chifeng Zhongtang Special Steel Co.Asian Metal Copyright released on November 27, 2018.

    Transfer

    Province (region, municipality)

    Company

    Location

    Facilities

    Capacity (10kt)

    Luanzhou, Hebei

    Tangshan Jinma Steel Group Co., Ltd.

    Ciyutuo Industrial Park

    1 blast furnace of 1#1,080 cubic meters; 1 blast furnace of 2#350 cubic meters;  1 blast furnace of 3#500 cubic meters  

    285

    Luanzhou, Hebei

    Tangshan Jinma Steel Group Co., Ltd.

    Ciyutuo Industrial Park

    1# converter of 120t; 2# converter of 120t

    270

    Transferee

    No.

    Province (region, municipality)

    Company

    Location

    Project

    Capacity (10kt)

    1

    Chifeng, Inner Mongolia

    Chifeng Zhongtang Special Steel Co., Ltd.

    Ningcheng, Chifeng

    High-quality steel project of Chifeng Zhongtang Special Steel Co., Ltd.

    285 of steel-making

    2

    Chifeng, Inner Mongolia

    Chifeng Zhongtang Special Steel Co., Ltd.

    Ningcheng, Chifeng

    High-quality steel project of Chifeng Zhongtang Special Steel Co., Ltd.

    270 of iron-making


    Note: Facilities and capacity after transfer subject to the announcement of Department of Industry and Information Technology of Inner Mongolia.