• NCM 523 Delivered Chinaup(2900)  10-28|NCM 613 Delivered Chinaup(2700)  10-28|Terbium Oxide 99.99%min EXW Chinadown(-200)  10-28|Erbium Oxide 99.5%min FOB Chinaup(1.5)  10-28|Cobalt Carbonate 46%min Delivered Chinaup(5000)  10-28|Gadolinium Oxide 99.99%min In Warehouse Baltimoreup(5)  10-28|Cobalt Metal 99.8%min In warehouse Rotterdamup(0.6)  10-28|Lithium Cobaltate Co 60%min Delivered Chinaup(10)  10-28|Cobalt Oxide 72%min In warehouse Rotterdamup(0.9)  10-28|NCM 8312 Delivered Chinaup(3000)  10-28|Praseodymium Oxide 99.5%min In warehouse Rotterdamup(2)  10-28|Cobalt Metal 99.8%min In warehouse Baltimoreup(0.6)  10-28|Sodium Pyroantimonate 58.4% Delivered Chinadown(-2000)  10-28|Coal Tar Pitch Coking Value 56%min EXW Chinadown(-100)  10-28
  • Capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel

    2019-11-06 15:59:41   [Print]
    On November 5, Department of Industry and Information Technology of Jiangsu sought public opinions on the capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng; the publication period is from November 5, 2019 to November 12, 2019.

    Capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng

    Construction of Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Yan Group Lianxin Steel

    Dafeng Port

    1 iron-making blast furnace of 1,200 cubic meters (3#)

    113

    October 2019

    December 2019

    1:1.25 for total capacity of 1.Asian Metal Copyright4125 million tons of 3# blast furnace will be transferred into 1.Asian Metal Copyright47 million tons; (1) 1.Asian Metal Copyright Capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng Construction of Project Company Location Facilities Transfer capacity 10kt Proposed construction date Proposed operation date Transfer ratio Yan Group Lianxin Steel Dafeng Port 1 iron-making blast furnace of 1,200 cubic meters 3# 113 October 2019 December 2019 1:1.Asian Metal Copyright4125 million tons of 3# blast furnace will be transferred into 1.13 million tons; (2) the rest of 57,700t (46,000t after transfer) will be used by the company

    Cancelled Projects of Technological Upgrading

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Start date

    Completion date

    Note

    1

    Yancheng

    Yan Group Lianxin Steel

    1 iron-making blast furnace of 1,080 cubic meters (3#)

    104

    October 2019

    December 2019

     

    2

    Yancheng

    Yan Group Lianxin Steel

    The rest of the pulication

    43

    /

    /

     

    Total

    /

    /

    147

    /

    /

     

    .Asian Metal Copyright Location Company Facilities Transfer capacity 10kt Start date Completion date Note 1 Yancheng Yan Group Lianxin Steel 1 iron-making blast furnace of 1,080 cubic meters 3# 104 October 2019 December 2019 2 Yancheng Yan Group Lianxin Steel The rest of the pulication 43 Total 147 Asian Metal Copyright