• Polysilicon 9N Delivered Chinaup(1)  07-03|Chrome Lump S.A. 38%min CIF Chinadown(-6)  07-03|Zircon Sand S.A. Zr(Hf)O2 65%min CIF Chinadown(-30)  07-03|Yttrium Oxide 99.999%min In warehouse Rotterdamup(0.3)  07-03|Calcium Ingot Reductive 98%min EXW Chinaup(350)  07-03|Iron Ore Fine Australian 62%min CNF Chinaup(2)  07-03|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinaup(10)  07-03|HR Coil SS400 3.0mm In warehouse Kuala Lumpurdown(-50)  07-03|Ferro-vanadium 80%min In warehouse Rotterdamdown(-0.5)  07-03|Medium Plate SS400 16mm In warehouse Kuala Lumpurdown(-50)  07-03|Spodumene Li2O 5%min In port Chinaup(15)  07-03|Zircon Sand S.A. Zr(Hf)O2 66%min CIF Chinadown(-30)  07-03|Zircon Sand Australian Zr(Hf)O2 66%min In port Chinadown(-30)  07-03|Fused Zirconia Zr(Hf)O2 98.5%min EXW Chinaup(500)  07-03
  • Capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel

    2019-11-06 15:59:41   [Print]
    On November 5, Department of Industry and Information Technology of Jiangsu sought public opinions on the capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng; the publication period is from November 5, 2019 to November 12, 2019.

    Capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng

    Construction of Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Yan Group Lianxin Steel

    Dafeng Port

    1 iron-making blast furnace of 1,200 cubic meters (3#)

    113

    October 2019

    December 2019

    1:1.25 for total capacity of 1.Asian Metal CopyrightOn November 5, Department of Industry and Information Technology of Jiangsu sought public opinions on the capacity transfer scheme for 3# blast furnace technological upgrading project of Yan Group Lianxin Steel in Yancheng; the publication period is from November 5, 2019 to November 12, 2019.Asian Metal Copyright47 million tons; (1) 1.Asian Metal Copyright13 million tons; 2 the rest of 57,700t 46,000t after transfer will be used by the company Cancelled Projects of Technological Upgrading No.Asian Metal Copyright4125 million tons of 3# blast furnace will be transferred into 1.13 million tons; (2) the rest of 57,700t (46,000t after transfer) will be used by the company

    Cancelled Projects of Technological Upgrading

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Start date

    Completion date

    Note

    1

    Yancheng

    Yan Group Lianxin Steel

    1 iron-making blast furnace of 1,080 cubic meters (3#)

    104

    October 2019

    December 2019

     

    2

    Yancheng

    Yan Group Lianxin Steel

    The rest of the pulication

    43

    /

    /

     

    Total

    /

    /

    147

    /

    /

     

    .Asian Metal Copyright4125 million tons of 3# blast furnace will be transferred into 1Asian Metal Copyright