On October 11, Department of Industry and Information Technology of Shandong Province unveiled and invited public review on the production capacity replacement plan for Shandong Taishan Steel Group
.Asian Metal Copyright
.
Asian Metal Copyright The review period will last from October 11 to November 7, 2019.
| Project to be constructed
|
| Company
|
Construction
site
|
Specifics on equipment to be constructed
|
Production capacity to be built
(10k tons)
|
Planned construction commencement time
|
Planned operation time
|
Replacement ratio
|
| Shandong Taishan Steel Group
|
Jinan city
|
Two revolving furnaces of 117t
|
264
|
2019
|
2022
|
To-be-built capacity should not excel to-be-replaced capacity
|
| Projects to be replaced
|
| No.
|
Province
|
Company
|
Specifics on equipment to be replaced
|
Production capacity to be replaced
(10k tons)
|
Planned dismantling commencement time
|
Planned dismantling completion time
|
Notes
|
| 1
|
Shandong province
|
Shandong Taishan Steel Group
|
Two revolving furnaces of 60t, and one revolving furnace of 70t
|
265
|
Before the to-be-built project is completely built
|
Before the to-be-built project is completely built
|
There will be a crude steel production capacity of 10,000t left, of which 1,000t will be used for the to-be-built project and 9,000t for the company's own 400 series stainless steel project.
|
.Asian Metal Copyright
Province
Company
Specifics on equipment to be replaced
Production capacity to be replaced
10k tons
Planned dismantling commencement time
Planned dismantling completion time
Notes
1
Shandong province
Shandong Taishan Steel Group
Two revolving furnaces of 60t, and one revolving furnace of 70t
265
Before the to-be-built project is completely built
Before the to-be-built project is completely built
There will be a crude steel production capacity of 10,000t left, of which 1,000t will be used for the to-be-built project and 9,000t for the company's own 400 series stainless steel projectAsian Metal Copyright