• NdFeB Sintered Rough N35 Block EXW Chinaup(4)  11-21|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max FOB Chinaup(0.3)  11-21|Lithium Hydroxide LiOH 56.5%min, Magnets 0.0001%max Delivered South Koreaup(0.3)  11-21|Ferro-vanadium 80%min In warehouse Pittsburghdown(-0.9)  11-21|Ferro-chrome Indian Cr 58%min, C 8%max CIF Chinadown(-0.03)  11-21|Spodumene Li2O 3%min In port Chinaup(30)  11-21|Cobalt Intermediate 30-40% CIF Chinaup(0.6)  11-21|Wire Rod SAE1008 5.5mm In warehouse Kuala Lumpurup(60)  11-21|Lithium Manganate Mn 58% Delivered Chinaup(900)  11-21|Spodumene Li2O 6%min CIF Chinaup(30)  11-21|Lithium Iron Phosphate Li 3.9%min Delivered Chinadown(-1000)  11-21|Thorium Tungsten Electrode ThO2 1.7-2.2% EXW Chinaup(20)  11-21|Rebar HRB400 20mm In warehouse Guangzhouup(80)  11-21|Samarium Cobalt 30H EXW Chinaup(7)  11-21
  • Shanghai Baoye Group wins Desheng Stainless Steel's bidding on blast furnace construction project

    2019-10-12 17:54:57   [Print]
    On October 10, Shanghai Baoye Group won the blast furnace construction project of Baosteel Desheng Stainless Steel Co.Asian Metal Copyright .Asian Metal Copyright, Ltd.Asian Metal Copyright It will be built in the plant site of Desheng Stainless Steel located in Luoyuan, Fujian, and the construction cycle will last for 497 days.Asian Metal Copyright, a subsidiary of China Baowu Steel Group Corporation.

    The project consists of one 2,500m3 blast furnace and its mating facilities, and will an annual production capacity of 2.241 million tons of melted iron.Asian Metal Copyright It will be built in the plant site of Desheng Stainless Steel located in Luoyuan, Fujian, and the construction cycle will last for 497 days.Asian Metal Copyright It will be built in the plant site of Desheng Stainless Steel located in Luoyuan, Fujian, and the construction cycle will last for 497 days.

    .Asian Metal Copyright, LtdAsian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.