• Yttrium Oxide 99.999%min In warehouse Rotterdamup(5)  11-27|Yttrium Oxide 99.999%min FOB Chinaup(0.5)  11-27|NdFeB Sintered Rough N45 Block EXW Chinaup(5)  11-27|NdFeB Sintered Rough 35M Block EXW Chinaup(5)  11-27|NdFeB Sintered Rough 50M Block EXW Chinaup(6)  11-27|NdFeB Sintered Rough N52 Block EXW Chinaup(6)  11-27|Erbium Oxide 99.5%min In warehouse Rotterdamup(2)  11-27|Indium Ingot 99.995%min Delivered Europeup(10)  11-27|Indium Ingot 99.995%min Delivered USup(10)  11-27|NdFeB Sintered Rough 45M Block EXW Chinaup(5)  11-27|Vanadium Pentoxide Flake 98%min EXW Chinaup(2000)  11-27|NdFeB Sintered Rough 48H Block EXW Chinaup(6)  11-27|NdFeB Sintered Rough 35H Block EXW Chinaup(5)  11-27|Gadolinium Oxide 99.99%min In Warehouse Baltimoreup(5)  11-27
  • Capacity transfer scheme for Baosteel Desheng Stainless Steel

    2019-09-18 17:19:40   [Print]
    On September 12, Department of Industry and Information Technology of Fujian sought public opinions on the capacity transfer scheme for Baosteel Desheng Stainless Steel Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright; the publication will last for 20 days.

    Iron and steel capacity transfer scheme for Baosteel Desheng Stainless Steel

    Construction of Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Baosteel Desheng Stainless Steel Co., Ltd.

    Luoyuan, Fuzhou

    1 blast furnace of 2500m3, 1 converter of 150t and 2 AOD furnaces of 120t

    Iron-making: 213; Steel-making: 322 (stainless steel)

    May 2019

    May 2021

    Iron-making: 1.005:1; Steel-making: 1.003:1

    Cancelled Projects

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

    Shanghai

    Baoshan Iron & Steel Co., Ltd.

    1 C3000 COREX furnace

    Iron-making: 150

    Before projection operation

    Before projection operation

    The rest of capacity will be used in other projects.

    2

    Shanghai

    Shanghai Baosteel Stainless Steel Co., Ltd.

    1 converter of 150t ; 2 electric furnaces of 100t

    Steel-making: 216

    3

    Wuhan, Hubei

    WISCO

    1 blast furnace of 2200m3; 2 converters of 90t

    Iron-making: 64; Steel-making: 107

    Total

    Iron-making: 214; Steel-making: 323

    /