Department of Industry and Information Technology of Ningxia Hui Autonomous Region announced the capacity replacement scheme for projects on 11 September with the publicity period from 11 September to 19 September, 2019.
Construction of Projects
|
Company
|
Location
|
Facility
|
Replaced capacity (10kt)
|
Proposed construction date
|
Proposed operation date
|
Replacement ratio
|
Ningxia Xinghua Iron & Steel Co., Ltd.
|
Shizuishan Economy & Technology Development Zone (in the old plant Ningxia Boyu Hongxing Special Steel Group Co., Ltd.)
|
1 blast furnace of 1,580m3;
1 converter of 138t
|
Blast furnace: 137
Converter: 150
|
Apr 2020
|
Dec 2021
|
Blast furnace: 1.022:1;
Converter: 1.013:1
|
Cancelled Projects
|
Region
|
Company
|
Facility
|
Replaced capacity (10kt)
|
Demolition start date
|
Demolition completion date
|
Note
|
Ningxia Hui Autonomous Region
|
Ningxia Boyu Hongxing Special Steel Group Co., Ltd.
|
2 blast furnaces of 600m3
|
140
|
Oct 2021
|
Nov 2021
|
|
Ningxia Boyu Hongxing Special Steel Group Co., Ltd.
|
2 converters of 50t
|
152
|
Oct 2021
|
Nov 2021
|
|