• Manganese Ore Gabonese 44%min In Qinzhou Port(3.1)  05-15|Manganese Ore Brazilian 44%min In Qinzhou Port(3.1)  05-15|Manganese Ore Gabonese 44%min In Tianjin Port(3.1)  05-15|Manganese Ore Brazilian 44%min In Tianjin Port(3.1)  05-15|Manganese Ore Australian 45%min In Qinzhou Port(3)  05-15|Manganese Ore Australian 45%min In Tianjin Port(3)  05-15|Copper Conc. TC 25%min CIF China(-1)  05-15|Antimony Trioxide 99.8%min Delivered China(3000)  05-15|Tungsten APT 88.5%min FOB China(10)  05-15|Lithium Carbonate 99.2%min Delivered China(-3000)  05-15|Lithium Carbonate 99.5%min Delivered China(-3000)  05-15|Tungsten Oxide WO3 99.95%min FOB China(10)  05-15|Tin Conc. Burmese 20%min In warehouse MengA(6000)  05-15|Lithium Manganate Mn 58% Delivered China(-1000)  05-15
  • Xusteel Group's phase III iron-making continuous casting project completes thermal load trial operation

    2020-12-02 11:14:21   [Print]
    On November 28, Xusteel Group's phase III iron-making continuous casting project contracted by MCC 17 Group Metallurgy Engineering Technology Branch completed thermal load trial operation.

    Xusteel Group's phase III iron-making continuous casting project plans to build an iron-making continuous casting steel structure plant, a converter of 120t, auxiliary system and other facilities.
    .Asian Metal Copyright Xusteel Group's phase III iron-making continuous casting project plans to build an iron-making continuous casting steel structure plant, a converter of 120t, auxiliary system and other facilitiesAsian Metal Copyright