• Ferro-manganese Mn 65%min, C 7%max EXW China(350)  05-09|Silico-manganese 65/17 EXW China(400)  05-09|Ferro-manganese Mn 75%min, C 8%max EXW China(350)  05-09|Silico-manganese 60/14 EXW China(300)  05-09|Manganese Ore Gabonese 44%min In Qinzhou Port(2)  05-09|Manganese Ore Gabonese 44%min In Tianjin Port(2)  05-09|Manganese Ore Brazilian 44%min In Qinzhou Port(2)  05-09|Manganese Ore Australian 45%min In Qinzhou Port(2)  05-09|Manganese Ore Australian 45%min In Tianjin Port(2)  05-09|Manganese Ore Brazilian 44%min In Tianjin Port(2)  05-09|Manganese Ore Carbonate, Mn 13%min EXW China(1.3)  05-09|Manganese Sulfate Mn 32%min EXW China(200)  05-09|Manganese Ore S.A. 36%min In Qinzhou Port(1.5)  05-09|Manganese Ore S.A. 36%min In Tianjin Port(1.5)  05-09
  • Tianyuan Manganese Industry completes launching first stage silicomanganese production

    2020-08-25 08:34:56   [Print]
    BEIJING (Asian Metal) 25 Aug 20 – Ningxia Tianyuan Manganese Industry Co.Asian Metal Copyright The company started commercial production at the end of August and released the first batch of silicomanganese products on September 1st.Asian Metal Copyright, Ltd.Asian Metal Copyright They would use their own Ghanaian mine 25% as raw materials for production.Asian Metal Copyright a new silicomanganese producer in West China with production capacity of 300,000t, would complete launching the first stage production at the end of August, with the output of about 8,000t in September.

    The company started commercial production at the end of August and released the first batch of silicomanganese products on September 1st. They plan to put the entire plant into production with three stages and maintain two submerged arc furnaces of 30,000kVA for silicomanganese production every stage.Asian Metal Copyright, Ltd.Asian Metal Copyright "We finished heating the submerged arc furnaces on August 20th and would complete launching the first stage production at the end of August.Asian Metal Copyrighta new silicomanganese producer in West China with production capacity of 300,000t, would complete launching the first stage production at the end of August, with the output of about 8,000t in September.Asian Metal Copyright We expect to produce about 8,000t in September," said a source from the company, expecting that they would start the second stage production at the end of September and the third stage production at the end of October.

    With an annual production capacity of 300,000t of silicomanganese 65/17, the company has six submerged arc furnaces of 30,000kVA for silicomanganese production. They would use their own Ghanaian mine 25% as raw materials for production.

    Currently, the mainstream prices of Chinese silicomanganese 65/17 stand at RMB6,000-6,200/t (USD858-887/t) EXW D/P, unchanged from last week. 
    .Asian Metal Copyright They plan to put the entire plant into production with three stages and maintain two submerged arc furnaces of 30,000kVA for silicomanganese production every stageAsian Metal Copyright
    Silico-manganese 65/17 In warehouse Pittsburgh
    Unit:USD/lb
    China silicomanganese producers' sales to production ratio statistics by province by month