Zenith Steel commences construction of green fine-steel coking project
2020-07-06 17:24:43 [Print]
On July 3, Zenith Steel commenced construction of its green fine-steel coking project at Nantong city
Four coking furnaces of 7-meter height, reheating and large volume and their matching gas purifying facilities will be built for the project; and the project is built, it will have an annual production capacity of 3.4 million tons of coke and will have two matching units of dry quenching facilities with a processing capacity of 220t/h.
. Construction of the project is contracted to MCC Coking And Refractory Engineering Consulting Corporation.
Four coking furnaces of 7-meter height, reheating and large volume and their matching gas purifying facilities will be built for the project; and the project is built, it will have an annual production capacity of 3.4 million tons of coke and will have two matching units of dry quenching facilities with a processing capacity of 220t/h.