On February 25, Department of Industry and Information Technology of Hebei sought public opinions on the coke capacity transfer scheme of Hebei Huafeng Energy Technology Development Co
.Asian Metal Copyright, Ltd.
Asian Metal Copyright, Ltd.
Construction of project (newly built)
|
Company
|
Location
|
Capacity (10kt)
|
Proposed start time
|
Proposed operation time
|
Transfer ratio
|
Hebei Huafeng Energy Technology Development Co., Ltd.
|
Plant of Hebei Huafeng in Wu'an
|
100
|
After approval
|
December 2020
|
1.25 : 1
|
Total
|
|
10
|
|
|
|
Canceled project
|
No.
|
Location
|
Company
|
Capacity (10kt)
|
Demolition start time
|
Demolition end time
|
Note
|
1
|
Wu'an in Handan
|
Hebei Huafeng Energy Technology Development Co., Ltd.
|
96
|
Before operation of the new project
|
December 31, 2020
|
|
2
|
Fengfeng mining area in Handan
|
Handan Fengfeng Pengtong Coking Co., Ltd.
|
29
|
Before operation of the new project
|
December 31, 2020
|
670,000t of capacity in total, including 290,000t for transfer in this project
|
Total
|
|
|
125
|
|
|
|
.Asian Metal Copyright
Plant of Hebei Huafeng in Wu'an
100
After approval
December 2020