• Copper Conc. TC 25%min CIF China(-1)  05-17|Nickel Cathode Norilsk 99.96%min In port China(4300)  05-17|Indium Ingot 99.995%min Delivered Europe(8)  05-17|TMT Bar Fe500 16mm In warehouse Mumbai(1500)  05-17|Nickel Cathode 99.96%min EXW China(4300)  05-17|TMT Bar Fe500 12mm In warehouse Mumbai(1500)  05-17|Indium Ingot 99.995%min FOB China(10)  05-17|Rebar HRB400 20mm FOB China(15)  05-17|Wire Rod SAE1008 5.5mm In warehouse Mumbai(1500)  05-17|Wire Rod Q195 6.5mm FOB China(15)  05-17|Wire Rod SAE1008 6.5mm FOB China(15)  05-17|Rebar HRB400 12mm FOB China(15)  05-17|Indium Ingot 99.995%min Delivered US(7)  05-17|Cobalt Metal 99.8%min Delivered China(5)  05-17
  • Electric furnace steel-making capacity transfer scheme for Guangdong Jinshenglan Metallurgy Technology

    2019-09-18 17:40:36   [Print]
    On September 11, Department of Industry and Information Technology of Guangdong sought public opinions on the capacity transfer scheme of Guangdong Jinshenglan Metallurgy Technology Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright Capacity transfer scheme of Guangdong Jinshenglan Metallurgy Technology Co.Asian Metal Copyright to build a 150t of electric furnace for steel-making; the publication period is from September 11, 2019 to October 16, 2019.

    Capacity transfer scheme of Guangdong Jinshenglan Metallurgy Technology Co., Ltd. to build a 150t of electric furnace for steel-making

    Construction of Project

    Company

    Location

    Facilities

    Transfer capacity (10kt)

    Proposed construction date

    Proposed operation date

    Transfer ratio

    Guangdong Jinshenglan Metallurgy Technology Co., Ltd.

    Yunfu, Guangdong

    1 electric furnace of 150t

    120

    November 2019

    May 2021

    1.001: 1

    Cancelled Projects

    No.

    Location

    Company

    Facilities

    Transfer capacity (10kt)

    Demolition start date

    Demolition completion date

    Note

    1

     

    Xinjiang

     

    Xinjiang Qinggang Iron and Steel Co., Ltd.

    1 converter of 40t

    50

    Before operation of new project

    Before operation of new project

    The total cancelled capacity is 1.25 million tons, including 1.Asian Metal Copyright 1 converter of 50t 75 Before operation of new project Before operation of new project Total 125 Note: 1.Asian Metal Copyright2013 million tons for capacity transfer of the mentioned project.Asian Metal Copyright to build a 150t of electric furnace for steel-making; the publication period is from September 11, 2019 to October 16, 2019.Asian Metal Copyright The rest of 48,700t will be used in capacity transfer for future projects.

    2

    Xinjiang

    Xinjiang Kunyu Iron and Steel Co., Ltd.

    1 converter of 50t

    75

    Before operation of new project

    Before operation of new project

    Total

    /

    /

    /

    125

    /

    /


    Note: 1. The capacity to be cancelled or built in transfer should be calculated based on the documents from Ministry of Industry and Information Technology.Asian Metal Copyright, Ltd.Asian Metal Copyright The documents only provide reference for transfer ratio.
    .Asian Metal Copyright The documents only provide reference for transfer ratioAsian Metal Copyright