• Aluminum Alloy TC A356.2 Delivered Chinaup(20)  10-31|Magnesia E.F. 97%min EXW Chinaup(100)  10-31|Antimony Ingot 99.65%min In warehouse Rotterdamup(1000)  10-31|Magnesia E.F. 97%min H-Ca EXW Chinaup(100)  10-31|Antimony Trioxide 99.5%min In warehouse Rotterdamup(0.7)  10-31|Magnesia E.F. 97%min H-Ca FOB Chinaup(15)  10-31|Antimony Trioxide 99.5%min FOB Chinaup(600)  10-31|Antimony Trioxide 99.5%min In warehouse Baltimoreup(0.3)  10-31|Yttrium Oxide 99.999%min EXW Chinadown(-1000)  10-31|Magnesia C.C. 85%min 200mesh EXW Chinaup(20)  10-31|Chromic Anhydride 99.8%min EXW Chinadown(-500)  10-31|Magnesia C.C. 90%min 200mesh EXW Chinaup(20)  10-31|Indium Ingot 99.995%min EXW Chinadown(-50)  10-31|Medium Plate SS400 10mm FOB Chinadown(-10)  10-31
  • Wolf Minerals prepares to start production at the Hemerdon Project in Q3 2015

    2015-02-24 17:08:32   [Print]
    LONDON (Asian Metal) 24 Feb 15 - Wolf Minerals Limited (ASX: WLF, AIM: WLFE) indicated in a corporate presentation that the Hemerdon Project, a tungsten and tin project based in England, is on target for production in Q3 this year.Asian Metal Copyright 80% of the tungsten concentrate is supplied to GTP Plansee and Wolfram Berbau und Hutten Sandvik with a five year delivery schedule in placed, while an agreement is signed with Traxys for the tin marketing.Asian Metal Copyright Majority of the constructions at the site in Devon, including haul road, top soil removal, concrete, high voltage power and equipment delivery, are completed with structural steel erection and mine waste facility at 80% and 60% complete respectively.

    The Hemerdon mine is forecasted to produce 3 million tonnes of ore each year, with a WO3 production of 3,450 tonnes and tin production of 460 tonnes each annum by onsite facilities. 80% of the tungsten concentrate is supplied to GTP (Plansee) and Wolfram Berbau und Hutten (Sandvik) with a five year delivery schedule in placed, while an agreement is signed with Traxys for the tin marketing.

    According to the company’s cost calculation, the total production cost of the WO3, including the tin credits, is at USD170/mtu. Asian Metal is reporting WO3 50%min at USD210-230/mtu

    .Asian Metal Copyright The Hemerdon mine is forecasted to produce 3 million tonnes of ore each year, with a WO3 production of 3,450 tonnes and tin production of 460 tonnes each annum by onsite facilitiesAsian Metal Copyright
    Tin Conc. Burmese 20%min In warehouse MengA
    Unit:RMB/mtm
    Tin Conc. Burmese 20%min In warehouse MengA RMB/mtm
    China tin concentrate producers' inventory to production ratio statistics by province by month
    Unit: %
      Copyright © Asian Metal Ltd All rights reserved.