• Calcium Ingot Reductive 98%min EXW Chinaup(450)  07-02|Silicon Metal 7-8-3 Ex-VAT FOB Chinaup(30)  07-02|Silicon Metal 5-5-3 Ex-VAT FOB Chinaup(30)  07-02|Lithium Carbonate 99.2%min Delivered Chinaup(1500)  07-02|Silicon Metal 7-8-3 FOB Chinaup(30)  07-02|Silicon Metal 4-4-1 Ex-VAT FOB Chinaup(30)  07-02|Silicon Metal 5-5-3 FOB Chinaup(30)  07-02|Lithium Carbonate 99.5%min Delivered Chinaup(1500)  07-02|Silicon Metal 4-4-1 FOB Chinaup(30)  07-02|Bismuth Ingot 99.99%min EXW Chinadown(-3000)  07-02|Yttrium Oxide 99.999%min FOB Chinaup(0.2)  07-02|Yttrium Oxide 99.999%min In warehouse Rotterdamup(0.3)  07-02|Silicon Metal 3-3-03 Ex-VAT FOB Chinaup(30)  07-02|Bismuth Oxide 99.9%min EXW Chinadown(-3000)  07-02
  • Wolf Minerals prepares to start production at the Hemerdon Project in Q3 2015

    2015-02-24 17:08:32   [Print]
    LONDON (Asian Metal) 24 Feb 15 - Wolf Minerals Limited (ASX: WLF, AIM: WLFE) indicated in a corporate presentation that the Hemerdon Project, a tungsten and tin project based in England, is on target for production in Q3 this year.Asian Metal Copyright According to the company’s cost calculation, the total production cost of the WO3, including the tin credits, is at USD170mtu.Asian Metal Copyright Majority of the constructions at the site in Devon, including haul road, top soil removal, concrete, high voltage power and equipment delivery, are completed with structural steel erection and mine waste facility at 80% and 60% complete respectively.

    The Hemerdon mine is forecasted to produce 3 million tonnes of ore each year, with a WO3 production of 3,450 tonnes and tin production of 460 tonnes each annum by onsite facilities. 80% of the tungsten concentrate is supplied to GTP (Plansee) and Wolfram Berbau und Hutten (Sandvik) with a five year delivery schedule in placed, while an agreement is signed with Traxys for the tin marketing.

    According to the company’s cost calculation, the total production cost of the WO3, including the tin credits, is at USD170/mtu. Asian Metal is reporting WO3 50%min at USD210-230/mtu

    .Asian Metal Copyright Majority of the constructions at the site in Devon, including haul road, top soil removal, concrete, high voltage power and equipment delivery, are completed with structural steel erection and mine waste facility at 80% and 60% complete respectivelyAsian Metal Copyright
    Tin Solder Wire Sn 99%min, Ag 0.3%min, Cu 0.7%max EXW China
    Unit:RMB/kg
    Tin Solder Wire Sn 99%min, Ag 0.3%min, Cu 0.7%max EXW China RMB/kg
    China tin concentrate producers' sales volume statistics by province by month
    Unit: mt
      Copyright © Asian Metal Ltd All rights reserved.