• Selenium Dioxide 98%min Delivered China(5)  07-26|Arsenic Metal 99%min FOB China(-25)  07-26|Rhenium APR 99.99%min EXW China(140)  07-26|HR Strip Q195 295*2.5mm In warehouse Guangzhou(-100)  07-26|HR Strip Q195 685*2.75mm In warehouse Guangzhou(-100)  07-26|HR Strip Q195 295*2.5mm In warehouse Shanghai(-100)  07-26|HR Strip Q235B 685*5.5mm In warehouse Shanghai(-100)  07-26|Met. Coke A 13%max, S 0.7%max EXW Shanxi(-50)  07-26|Met. Coke A 13%max, S 0.7%max EXW Hebei(-50)  07-26|Met. Coke A 13%max, S 0.7%max EXW Shandong(-50)  07-26|Selenium Powder 99.9%min Delivered India(50)  07-26|Titanium Plate TA2 2mm EXW China(-2)  07-26|Ferro-silicon 65%min In warehouse Russia(-2)  07-26|Manganese Flake 99.7%min In warehouse Rotterdam(-50)  07-26
  • Zenith Nantong to replace 750ktpa of steel capacity

    2023-12-27 11:57:24   [Print]
    In accordance with relevant guidelines and implementation measures issued by the State Council, the steelmaking capacity replacement scheme by Zenith Steel Group (Nantong) Co.Asian Metal CopyrightIn accordance with relevant guidelines and implementation measures issued by the State Council, the steelmaking capacity replacement scheme by Zenith Steel Group Nantong Co.Asian Metal Copyright, Ltd.Asian Metal Copyright would close two 50-ton rotary furnaces with a combined capacity of around 1.Asian Metal Copyright has been made public by the Department of Industry and Information Technology of Jiangsu Province.

    Zenith Nantong plans to build a 100-ton electric furnace with steelmaking capacity of 750,000 tonnes per annum (Mtpa) through a capacity replacement program where Wuxi Xinsanzhou Special Steel Co., Ltd.Asian Metal Copyright Zenith Nantong plans to build a 100-ton electric furnace with steelmaking capacity of 750,000 tonnes per annum Mtpa through a capacity replacement program where Wuxi Xinsanzhou Special Steel Co.Asian Metal Copyright would close two 50-ton rotary furnaces with a combined capacity of around 1.Asian Metal Copyright would shut down capacity of 42,500tpa, of which 1.Asian Metal Copyright1Mtpa and Zenith Steel Group Co.Asian Metal Copyright1Mtpa and Zenith Steel Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal Copyright would shut down capacity of 42,500tpa, of which 1.Asian Metal Copyright, Ltd.Asian Metal Copyright125Mtpa will be replaced at the ratio of 1.Asian Metal Copyright, Ltd.Asian Metal Copyright5:1.

    Construction of the new furnace is scheduled to begin in June 2024, with capacity expected to come on stream in April 2025.

    .Asian Metal CopyrightIn accordance with relevant guidelines and implementation measures issued by the State Council, the steelmaking capacity replacement scheme by Zenith Steel Group Nantong CoAsian Metal Copyright
      Copyright © Asian Metal Ltd All rights reserved.