• Silico-manganese 65/17 EXW China(300)  04-25|Silico-manganese 60/14 EXW China(200)  04-25|Indium Ingot 99.995%min FOB China(9)  04-25|Molybdenum Conc. 45%min EXW China(100)  04-25|Steel Scrap MMS 4-6mm EXW Guangzhou(80)  04-25|Molybdenum Oxide 50%min EXW China(100)  04-25|Zirconium Sponge Zr+Hf 99.4%min EXW China(-5)  04-25|Ferro-silicon 75%min In warehouse Pittsburgh(0.03)  04-25|Iron Ore Fine Australian 62%min CNF China(3)  04-25|Ferro-molybdenum 60%min EXW China(6000)  04-25|Indium Ingot 99.995%min EXW China(60)  04-25|Copper Conc. TC 25%min CIF China(-1)  04-25|Calcium-silicon 30-60 FOB China(40)  04-25|Molybdenum Oxide 57%min In port South Korea(0.5)  04-25
  • Fuhua New Materials Group's steelmaking capacity replacement scheme made public

    2022-05-06 17:03:17   [Print]
    In accordance with relevant guidelines and implementation measures issued by the State Council, the capacity replacement scheme for a steelmaking project between Fujian Fuhua New Materials Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal CopyrightIn accordance with relevant guidelines and implementation measures issued by the State Council, the capacity replacement scheme for a steelmaking project between Fujian Fuhua New Materials Group Co.Asian Metal Copyright and Fuan Tongkang Metal Products Co.Asian Metal Copyright, Ltd.Asian Metal Copyright, Ltd.Asian Metal CopyrightIn accordance with relevant guidelines and implementation measures issued by the State Council, the capacity replacement scheme for a steelmaking project between Fujian Fuhua New Materials Group Co.Asian Metal Copyright was made public by the Economy and Information Technology Department of Fujian Province on April 30.

    According to the scheme, Fujian Fuhua New Materials and Fuan Tongkang Metal Products will shut down steelmaking capacity of 500,000tpa and 360,000tpa respectively, for a total of 860,000tpa.

    Fujian Fuhua New Materials will build new capacity of 825,000tpa to replace the capacity to be shut down at the ratio of 1:1, with the remaining capacity of 35,000tpa to be replaced for other projects.

    The newly-planned capacity is scheduled to be constructed in June 2023 with production expected by June 2026.

    .Asian Metal Copyright According to the scheme, Fujian Fuhua New Materials and Fuan Tongkang Metal Products will shut down steelmaking capacity of 500,000tpa and 360,000tpa respectively, for a total of 860,000tpaAsian Metal Copyright