Longxin Iron and Steel's capacity replacement scheme for 70-ton electric furnace upgrade project made public
2022-04-22 15:21:45 [Print]
In accordance with relevant guidelines and implementation measures issued by the State Council, Anhui Jingxian Longxin Iron and Steel's capacity replacement scheme for 70-ton electric furnace upgrade project will be made public by the Economy and Information Technology Department of Anhui Province from April 21 to May 19, 2022.
According to the scheme, Longxin Iron and Steel will build new capacity of 500,000tpa to replace the existing capacity of 500,000tpa to be shut down at the ratio of 1:1. The newly-planned capacity will be constructed in December 2022 with production expected by December 2024.