Fuxin Iron & Steel's capacity replacement project made public
2022-04-07 17:30:01 [Print]
In accordance with relevant guidelines and implementation measures issued by the State Council, the capacity replacement program of the electric arc furnace upgrading and rebuilding project of Longnan Fuxin Iron & Steel Co
According to the replacement program, Longnan Fuxin Iron & Steel will shut down steelmaking capacity of 1 million tons per annum (mtpa) and build capacity of 1.5 mtpa; Jiangxi Yuanxing Iron & Steel will shut down 0 . 5 mtpa of capacity . The ratio of the replacement is 1:1.
. , Ltd . was made public by the Department of Industry and Information Technology of Jiangxi Province on April 2.