12th Rare Earth Summit

May 27-28, 2021
Hangzhou, Zhejiang, China

11th Aluminum Raw Materials Summit

May 20-21, 2021
Hangzhou, Zhejiang, China

9th Magnesium Summit

April 15-16, 2021
Hangzhou, Zhejiang, China

13th World InBiGeGa Forum

March 25-26, 2021
Hangzhou, Zhejiang, China

7th World Antimony Forum

June 13-14, 2019
Changsha, Hunan, China

7th Refractory & Abrasive Materials Summit 2019

May 23-24, 2019
Qingdao, Shandong, China

10th Aluminum Raw Materials Summit

May 16-17, 2019
Zhengzhou, Henan, China

11th Rare Earth Summit

May 9-10, 2019
Qingdao, Shandong, China

8th Magnesium Summit

April 11-12, 2019
Zhuhai, Guangdong, China

12th World InBiGeGa Forum

March 14-15, 2019
Zhuhai, Guangdong, China

6th World Manganese & Selenium Forum

May 21-22, 2018
Hainan Sanya, China

Capacity transfer scheme of Rizhao Steel Holding Group

2019-11-15 17:14:39   【Print】
On November 13, Department of Industry and Information Technology of Shandong sought public opinions on the capacity transfer scheme of Rizhao Steel Holding Group Co.Asian Metal Copyright 2 Shandong Shandong Chuanyang Group Co.Asian Metal Copyright, Ltd.Asian Metal Copyright 2 Shandong Shandong Chuanyang Group Co.Asian Metal Copyright; the publication period is from November 13, 2019 to December 10, 2019.

Construction of Project

Company

Location

Facilities

Capacity (10kt)

Proposed construction time

Proposed operation time

Transfer Ratio

Rizhao Steel Holding Group Co., Ltd.

Lanshan District, Rizhao

2 blast furnaces of 3,000 cubic meters; 2 converters of 300t

500 of iron-making; 600 of steel-making

2020

2022

Reduction

Cancelled Project

No.

Province

Company

Facilities

Capacity (10kt)

Demolition start date

Demolition completion date

Notes

1

Shandong

Shandong Guangfu Group Co., Ltd.

2 blast furnaces of 450 cubic meters, 3 blast furnaces of 750 cubic meters; 1 converter of 60t; 2 converters of 80t; 1 electric furnace of 50t; 1 electric furnace of 100t

350 of iron-making; 396 of steel-making

Before the completion of the construction project

Before the completion of the construction project

1,000t of steel-making capacity and 1,000t of iron-making capacity was reduced in the capacity transfer. The rest capacity of 689kt iron-making and 659kt of steel-making will be left for future transfer.

2

Shandong

Shandong Chuanyang Group Co., Ltd.

3 blast furnaces of 630 cubic meters; 2 converters of 120t

219 of iron-making; 270 of steel-making

Before the completion of the construction project

Before the completion of the construction project