• Manganese Ore Gabonese 44%min In Tianjin Port(1.5)  04-19|Manganese Ore Australian 45%min In Qinzhou Port(1.5)  04-19|Manganese Ore Gabonese 44%min In Qinzhou Port(1.5)  04-19|Manganese Ore Brazilian 44%min In Tianjin Port(1.5)  04-19|Manganese Ore Australian 45%min In Tianjin Port(1.5)  04-19|Ferro-chrome Cr 60%min, C 0.1%max In warehouse Rotterdam(-0.1)  04-19|Manganese Ore S.A. 36%min In Tianjin Port(1.3)  04-19|Manganese Ore Brazilian 44%min In Qinzhou Port(1.3)  04-19|Manganese Sulfate Mn 32%min EXW China(150)  04-19|Copper Conc. 20%min Delivered China(2150)  04-19|Manganese Ore S.A. 36%min In Qinzhou Port(1)  04-19|Manganese Ore S.A. 37%min In Qinzhou Port(1)  04-19|Manganese Ore S.A. 37%min In Tianjin Port(1)  04-19|Indium Ingot 99.995%min EXW China(60)  04-19
  • CHEC inks with ACG to build infrastructures for bauxite export project

    2017-04-27 17:45:06   [Print]
    China Harbour Engineering Company Ltd.Asian Metal Copyright “CHEC” signed a general contract concerning the construction of bauxite export project marine structure, “the project” with Alumina Company of Guinea “ACG” in Conakry, capital of Guinea, on 25th.Asian Metal Copyright (“CHEC”) signed a general contract concerning the construction of bauxite export project (marine structure, “the project”) with Alumina Company of Guinea (“ACG”) in Conakry, capital of Guinea, on 25th.Asian Metal Copyright The total signing price is USD65 million.Asian Metal Copyright The total signing price is USD65 million.

    According to information from both parties, the owner of the project is ACG, a subsidiary of Emirates Global Aluminium ("EGA") registered in Guinea. The project adopts the design-build method and the project content includes constructions of piers wharf, approach bridge, loading platform and other ancillary facilities, with a project term of 64 weeks.

    The project is expected to achieve an annual capacity of 12 million tons upon completion and directly create 4,000 of employment positions.

    .Asian Metal Copyright The project adopts the design-build method and the project content includes constructions of piers wharf, approach bridge, loading platform and other ancillary facilities, with a project term of 64 weeksAsian Metal Copyright